Regulation 2. Interpretation

Chapter 1 — Scope and definitions · Subject matter and definitions

Text in operation from 18 April 2016, as amended by the instruments the Irish Statute Book’s Legislation Directory lists. Where this page and the official publication differ, the official publication prevails: official text

(1) In these Regulations—

“accelerated procedure” means—

(a) an open procedure in which the contracting authority has exercised the power conferred by Regulation 27(3) to fix a time limit for the receipt of tenders that is shorter than the minimum specified in Regulation 27(1)(b),

(b) a restricted procedure in which the contracting authority has exercised the power conferred by Regulation 28(5) to fix a time limit—

(i) for the receipt of requests to participate that is shorter than the minimum specified in Regulation 28(1)(b); or

(ii) for the receipt of tenders that is shorter than the minimum specified in Regulation 28(1)(e), or

(c) a competitive procedure with negotiation in which the contracting authority has exercised the power conferred by Regulation 28(5) to fix a time limit—

(i) for the receipt of requests to participate that is shorter than the minimum specified in Regulation 29(4), or

(ii) for the receipt of initial tenders that is shorter than the minimum specified in Regulation 29(5);

“advanced electronic signature” has the same meaning as it has in the Electronic Commerce Act 2000 (No. 27 of 2000);

“ancillary purchasing activity” means an activity consisting of the provision of support to purchasing activities, in particular in the following forms:

(a) technical infrastructure enabling contracting authorities to award public contracts or to conclude framework agreements for works, supplies or services;

(b) advice on the conduct or design of procurement procedures;

(c) preparation and management of procurement procedures on behalf and for the account of the contracting authority concerned;

“Award of Contracts by Utilities Regulations” means the European Union (Award of Contracts by Utility Undertakings) Regulations 2016;

“body governed by public law” means a body that has the following characteristics:

(a) it is established for the specific purpose of meeting needs in the general interest, not having an industrial or commercial character;

(b) it has legal personality;

(c) it has any of the following characteristics:

(i) it is financed, for the most part, by the State, a regional or local authority, or by another body governed by public law;

(ii) it is subject to management supervision by an authority or body referred to in clause (i);

(iii) it has an administrative, managerial or supervisory board, more than half of whose members are appointed by the State, a regional or a local authority, or by another body governed by public law;

“candidate” means an economic operator that has sought an invitation or has been invited to take part in a restricted or negotiated procedure, in a competitive dialogue or in an innovation partnership;

“central government authority” means a central government authority specified in Annex I to the Public Authorities Contracts Directive;

“centralised purchasing activity” means an activity conducted on a permanent basis, in one of the following forms:

(a) the acquisition of supplies or services, or the acquisition of supplies and services, intended for contracting authorities;

(b) the award of public contracts or the conclusion of framework agreements for works, supplies or services intended for contracting authorities;

“central purchasing body” means a contracting authority or a contracting entity within the meaning of Regulation 2(1) of the Award of Contracts by Utilities Regulations providing centralised purchasing activities and, possibly, ancillary purchasing activities;

“Commission” means the European Commission;

“Commission Decision 2009/767/EC” means Commission Decision of 16 October 2009 setting out measures facilitating the use of procedures by electronic means through the points of single contact under Directive 2006/123/EC of the European Parliament and of the Council on services in the internal market, as amended by Commission Decision of 28 July 2010, Commission Implementing Decision of 14 October 2013 and Commission Regulation (EU) No 519/2013 of 21 February 2013;

“Commission Decision 2011/130/EU” means Commission Decision 2011/130/EU of 25 February 2011 establishing minimum requirements for the cross-border processing of documents signed electronically by competent authorities under Directive 2006/123/EC of the European Parliament and of the Council on services in the internal market;

“common technical specification” means a technical specification in the field of ICT specified in accordance with Articles 13 and 14 of Regulation (EU) No 1025/2012 of 25 October 2012;

“company number” means the registration number of a company assigned to that company by the Companies Registration Office;

“competent authority” means—

(a) in relation to the State, an authority that is required or authorised to perform or exercise a particular function or power under a law or administrative provision of the State, or

(b) in relation to a Member State other than the State, an authority of that Member State that is required or authorised to perform or exercise a particular function or power under a law or administrative provision of that Member State;

“contracting authority” means—

(a) a State, regional or local authority,

(b) a body governed by public law, or

(c) an association formed by one or more such authorities or one or more such bodies governed by public law;

“contracting entity” means a person that—

(a) is a contracting authority or public undertaking which pursues one of the activities referred to in Regulations 10 to 16 of the Award of Contracts by Utilities Regulations 2016, or

(b) is not a contracting authority or public undertaking, but pursues one of the activities referred to in Regulations 10 to 16 of the Award of Contracts by Utilities Regulations 2016 or any combination thereof and has been granted special or exclusive rights by a competent authority of a Member State;

“corruption”, other than in Regulation 57, has the meaning given to it by the Convention drawn up on the basis of Article K.3 (2)(c) of the Treaty on European Union, on the fight against corruption involving officials of the European Communities or officials of Member States of the European Union drawn up under the Council Act of 26 May 1997;

“CPV” means the Common Procurement Vocabulary established by Regulation (EC) No 2195/2002;

“Defence Contract Regulations” means the European Union (Award of Contracts relating to Defence and Security) Regulations 2012 ( S.I. No. 62 of 2012 );

“design contests” means those procedures which enable the contracting authority to acquire, mainly in the fields of town and country planning, architecture, engineering or data processing, a plan or design selected by a jury after being put out to competition with or without the award of prizes;

“Directive 2002/21/EC” means Directive 2002/21/EC of the European Parliament and of the Council of 7 March 2002 on a common regulatory framework for electronic communications networks and services (Framework Directive);

“Directive 2004/39/EC” means Directive 2004/39/EC of the European Parliament and of the Council of 21 April 2004 on markets in financial instruments amending Council Directives 85/611/EEC and 93/6/EEC and Directive 2000/12/EC of the European Parliament and of the Council and repealing Council Directive 93/22/EEC, as amended by Directive 2006/31/EC of the European Parliament and of the Council of 5 April 2006, Directive 2007/44/EC of the European Parliament and of the Council of 5 September 2007, Directive 2008/10/EC of the European Parliament and of the Council of 11 March 2008, Directive 2009/65/EC of the European Parliament and of the Council of 13 July 2009 and Directive 2010/78/EU of the European Parliament and of the Council of 24 November 2010;

“Directive 2009/81/EC” means Directive 2009/81/EC of the European Parliament and of the Council of 13 July 2009 on the coordination of procedures for the award of certain works contracts, supply contracts and service contracts by contracting authorities or authorities in the fields of defence and security, and amending Directives 2004/17/EC and 2004/18/EC, as amended by Commission Regulation (EC) No 1177/2009 of 30 November 2009, Commission Regulation (EU) No 1251/2011 of 30 November 2011, Council Directive 2013/16/EU of 13 May 2013, Commission Regulation (EU) No 1336/2013 of 13 December 2013 and Commission Regulation (EU) 2015/2340 of 15 December 2015;

“Directive 2010/13/EU” means Directive 2010/13/EU of the European Parliament and of the Council of 10 March 2010 on the coordination of certain provisions laid down by law, regulation or administrative action in Member States concerning the provision of audiovisual media services;

“Directive 2012/34/EU” means Directive 2012/34/EU of the European Parliament and of the Council of 21 November 2012 establishing a single European railway area;

“Directive 77/249/EEC” means Council Directive 77/249/EEC of 22 March 1977 to facilitate the effective exercise by lawyers of freedom to provide services;

“disability” has the same meaning as it has in the Disability Act 2005 (No. 14 of 2005);

“disabled” means a disability in relation to a natural person;

“dynamic purchasing system” means the system referred to in Regulation 34;

“economic operator” means any natural or legal person or contracting authority, or a group of such persons or authorities, including temporary associations of undertakings, who or which offers—

(a) the execution of works or a work, or both, or

(b) the supply of products or the provision of services, on the market;

“electronic means” means electronic equipment for the processing (including digital compression) and storage of data which is transmitted, conveyed and received by wire, by radio, by optical means or by other electromagnetic means;

“ESPD” means the European Single Procurement Document referred to in Regulation 59(1);

“Europe 2020 strategy” means the Communication from the Commission of 3 March 2010 — Europe 2020 A strategy for smart, sustainable and inclusive growth (COM(2010) 2020 final);

“European Financial Stability Facility” means the société anonyme incorporated in Luxembourg (R.C.S. Luxembourg B153.414);

“European Stability Mechanism” means the international financial institution established as the European Stability Mechanism by Article 1 of the Treaty establishing the European Stability Mechanism done at Brussels on 2 February 2012 between the Euro Area Member States of the European Union;

“European standard” means a standard adopted by a European standardisation organisation and made available to the general public;

“European Technical Assessment” means the documented assessment of the performance of a construction product, in relation to its essential characteristics, in accordance with the respective European Assessment Document, as defined in point 12 of Article 2 of Regulation (EU) No 305/2011 of the European Parliament and of the Council of 9 March 2011;

“framework agreement” means an agreement between one or more contracting authorities and one or more economic operators, the purpose of which is to establish the terms governing contracts to be awarded during a given period, in particular with regard to price and, where appropriate, the quantities envisaged;

“GPA” means the Agreement on Government Procurement between certain parties to the World Trade Organisation done at Marrakesh on 15 April 1994, as amended by the Protocol Amending the Agreement on Government Procurement done at Geneva on 30 March 2012;

“innovation” means the implementation of a new or significantly improved product, service or process, including production, building or construction processes, a new marketing method or a new organisational method in business practices, workplace organisation or external relations, amongst other things, with the purpose of helping to solve societal challenges or to support the Europe 2020 strategy for smart, sustainable and inclusive growth;

“innovation partnership” shall be construed in accordance with Regulation 31;

“international standard” means a standard adopted by an international standardisation organisation and made available to the general public;

“invitation to confirm interest” means the invitation described in Regulation 54;

“label” means any document, certificate or attestation confirming that the works, products, services, processes or procedures in question meet certain requirements;

“label requirements” means the requirements to be met by the works, products, services, processes or procedures in question in order to obtain the label concerned;

“life cycle” means all consecutive or interlinked stages, including research and development to be carried out, production, trading and its conditions, transport, use and maintenance, throughout the existence of the product or the works or the provision of the service, from raw material acquisition or generation of resources to disposal, clearance and end of service or utilisation;

“local authority”, in relation to the State, has the same meaning as it has in the Local Government Act 2001 (No. 37 of 2001);

“Member State” means a Member State of the European Union and, where relevant, includes a contracting party to the Agreement on the European Economic Area signed at Oporto on 2 May 1992 (as adjusted by the Protocol signed at Brussels on 17 March 1993), as amended;

“Minister” means the Minister for Public Expenditure and Reform;

“money laundering” has the meaning given to it by Article 1 of Directive 2005/60/EC of the European Parliament and of the Council of 26 October 2005 on the prevention of the use of the financial system for the purpose of money laundering and terrorist financing;

“national standard” means a standard adopted by a national standardisation organisation and made available to the general public;

“negotiated procedure” means a procedure in accordance with Regulation 29 or 32;

“Official Journal” means the Official Journal of the European Union;

“open procedure” shall be construed in accordance with Regulation 27;

“prescribed civil engineering activities” means civil engineering activities listed in Schedule 1;

“prior information notice” means the notice referred to in Regulations 48 or 75(1)(b);

“procurement” means the acquisition by means of a public contract of works, supplies or services by one or more contracting authorities from economic operators chosen by those contracting authorities, whether or not the works, supplies or services are intended for a public purpose;

“procurement document” means any document produced or referred to by a contracting authority to describe or determine elements of a procurement or a procedure, including the contract notice, the prior information notice where it is used as a means of calling for competition, the technical specifications, the descriptive document, proposed conditions of contract, formats for the presentation of documents by candidates and tenderers, information on generally applicable obligations and any additional documents;

“procurement service provider” means a public or private body, which offers ancillary purchasing activities on the market;

“Public Authorities Contracts Directive” means Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC;

“public authority” means any body corporate, not having an industrial or commercial character that is established for a public purpose and—

(a) is financed wholly or substantially by the State, a local or regional authority or another public authority; or

(b) is subject to management supervision by such a body, or

(c) has an administrative, managerial or supervisory board, more than half of whose members are appointed by the State, a local or regional authority or another public authority, and, in particular, includes any body listed in Annex I to the Public Authorities Contracts Directive;

“public contract” means a contract for pecuniary interest concluded in writing between one or more economic operators and one or more contracting authorities and having as their object the execution of works, the supply of products or the provision of services;

“public service contract” means a public contract having as its object the provision of services other than those referred to in the definition of “public works contract";

“public supply contract” means a public contract having as its object the purchase, lease, rental or hire-purchase, with or without an option to buy, of a product and, for the purposes of this definition may include siting and installation operations;

“public undertaking” has the meaning given by Regulation 2 of the Award of Contracts by Utilities Regulations;

“public works contract” means a public contract having as its object one or more of the following:

(a) the execution, or both the design and execution, of works related to one of the activities listed in Schedule 1;

(b) the execution, or both the design and execution, of a work;

(c) the realisation, by whatever means, of a work corresponding to the requirements specified by the contracting authority exercising a decisive influence on the type or design of the work;

“Publications Office” means the Publications Office of the European Union;

“quarter” means a period of 3 months ending in March, June, September or December in any year;

“regional authority” includes an authority of an administrative unit classified as NUTS level 1 or 2 in accordance with Regulation (EC) No 1059/2003 of the European Parliament and of the Council of 26 May 2003 on the establishment of a common classification of territorial units for statistics (NUTS);

“Regulation (EC) No 2195/2002” means Regulation (EC) No 2195/2002 of the European Parliament and of the Council of 5 November 2002 on the Common Procurement Vocabulary (CPV), as amended by Commission Regulation (EC) No 2151/2003 of 16 December 2003, Commission Regulation (EC) No 213/2008 of 28 November 2007 and Regulation (EC) No 596/2009 of the European Parliament and of the Council of 18 June 2009;

“Regulations of 2006” mean the European Communities (Award of Public Authorities Contracts) Regulations 2006 ( S.I. No. 329 of 2006 );

“selection criteria” means the criteria established by a contracting authority in accordance with Regulation 58;

“standard” means a technical specification, adopted by a recognised standardisation body, for repeated or continuous application, with which compliance is not compulsory, and which is one of the following:

(a) an international standard;

(b) a European standard;

(c) a national standard;

“sub-central contracting authority” means a contracting authority that is not a central government authority;

“technical reference” means any deliverable produced by European standardisation bodies, other than European standards, according to procedures adapted to the development of market needs;

“technical specification” means—

(a) in the case of public service contracts or public supply contracts a specification in a document defining the required characteristics of a product or a service, including quality levels, environmental and climate performance levels, design for all requirements (including accessibility for disabled persons) and conformity assessment, performance, use of the product, safety or dimensions, including requirements relevant to the product as regards the name under which the product is sold, terminology, symbols, testing and test methods, packaging, marking and labelling, user instructions, production processes and methods at any stage of the life cycle of the supply or service and conformity assessment procedures, or

(b) in the case of public works contracts, the totality of the technical prescriptions contained in particular in the procurement documents, defining the characteristics required of a material, product or supply, which permits a material, a product or a supply to be described in a manner such that it fulfils the use for which it is intended by the contracting authority; those characteristics include levels of environmental and climate performance, design for all requirements (including accessibility for disabled persons) and conformity assessment, performance, safety or dimensions, including the procedures concerning quality assurance, terminology, symbols, testing and test methods, packaging, marking and labelling, user instructions, and production processes and methods at any stage of the life cycle of the works; those characteristics also include rules relating to design and costing, the test, inspection and acceptance conditions for works and methods or techniques of construction and all other technical conditions which the contracting authority is in a position to prescribe, under general or specific regulations, in relation to the finished works and to the materials or parts which they involve;

“tenderer” means an economic operator that has submitted a tender;

“TFEU” means the Treaty on the Functioning of the European Union;

“Treaties” means the Treaty on European Union and the TFEU;

“Utilities Directive” means Directive 2014/25/EU of the European Parliament and of the Council of 26 February 2014 on procurement by entities operating in the water, energy, transport and postal services sectors and repealing Directive 2004/17/EC;

“VAT” means value-added tax;

“work” where used as a singular noun, means the outcome of building or civil engineering works taken as a whole which is sufficient in itself to fulfil an economic or technical function;

“works contracts” means contracts having as their object one of the following:

(a) the execution, or both the design and execution, of works related to one of the activities within the meaning of Schedule 1;

(b) the execution, or both the design and execution, of a work;

(c) the realisation by whatever means of a work corresponding to the requirements specified by the contracting authority exercising a decisive influence on the type or design of the work;

“working day” means a day which is not a Saturday, Sunday, Good Friday or a Bank Holiday;

“written” or “in writing” means any expression consisting of words or figures which can be read, reproduced and subsequently communicated, including information transmitted and stored by electronic means.

(2) A word or expression which is used in these Regulations and which is also used in the Public Authorities Contracts Directive has, unless the context otherwise requires, the same meaning in these Regulations as it has in that Directive.

Cross-references

Referred to by