When do the Regulations apply to a contract?

When a contracting authority awards a public contract or organises a design contest whose value, net of VAT, is estimated to be equal to or greater than the relevant threshold (Regulation 5), and no exclusion in Regulations 7 to 17 applies. A contracting authority is a State, regional or local authority, a body governed by public law, or an association of them (Regulation 2(1)).

Legal basisRegulation 5 · Regulation 2(1) · official text

Where do I find the threshold amounts?

On the thresholds page. The figures in Regulation 5 as made have since been revised by the European Commission, and that page shows both. Which threshold applies depends on the type of contract and on whether the buyer is a central government authority or a sub-central contracting authority (Regulation 5(b), Regulation 5(c)).

Legal basisRegulation 5(b) · Regulation 5(c) · official text

What is the difference between a central government authority and a sub-central contracting authority?

A central government authority is one specified in Annex I to the Public Authorities Contracts Directive; every other contracting authority is a sub-central contracting authority (Regulation 2(1)). The distinction sets the threshold for supply contracts, service contracts and design contests (Regulation 5(b), Regulation 5(c)).

Legal basisRegulation 2(1) · Regulation 5(b) · Regulation 5(c) · official text

Do options and renewals count towards the estimated value?

Yes. The estimate is based on the total amount payable, net of VAT, including any form of option and any renewal of the contract as explicitly specified in the procurement documents (Regulation 6(1)). Prizes or payments to candidates or tenderers are also counted (Regulation 6(2)).

Legal basisRegulation 6(1) · Regulation 6(2) · official text

At what moment is the estimated value fixed?

When the call for competition is sent or, where none is foreseen, when the contracting authority commences the procurement procedure, including, where appropriate, by contacting economic operators about it (Regulation 6(7)).

Legal basisRegulation 6(7) · official text

Can a contract be split to stay below the threshold?

No. A procurement must not be subdivided with the effect of preventing it from falling within the Regulations, other than where the subdivision is justified by objective reasons (Regulation 6(6)), and the method of calculation must not be chosen with the intention of excluding it (Regulation 6(5)).

Legal basisRegulation 6(6) · Regulation 6(5) · official text

How are lots treated?

The values of all the lots are added together, and if the total reaches the relevant threshold the Regulations apply to the awarding of each lot (Regulation 6(11)(b), Regulation 6(12)(b)). Small lots may be awarded without the Regulations’ procedures within the limits of Regulation 6(13), which the guide on thresholds and estimated value explains.

Legal basisRegulation 6(11)(b) · Regulation 6(12)(b) · Regulation 6(13) · official text

How is a framework agreement valued?

At the maximum estimated value, net of VAT, of all the contracts envisaged for the total term of the framework agreement; the same rule applies to a dynamic purchasing system (Regulation 6(8)).

Legal basisRegulation 6(8) · official text

Can a public body award a contract to a company it controls without a tender?

Yes, if all the conditions of Regulation 12(1) are met: control similar to that over its own departments, more than 80% of the company’s activities carried out for the controlling authority or other legal persons it controls, and no direct private capital participation other than the limited forms the Regulation allows. The guide on exemptions covers this and the other public-public exclusions of Regulation 12.

Legal basisRegulation 12(1) · official text