Practical guide

Time limits for tenders

How a contracting authority sets the time limits for tenders and requests to participate, the minimum time limits of each procedure, when they may be shortened or must be extended, and the standstill period before the contract is concluded.

Updated 20 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026

Legal basisRegulation 47(1) · Regulation 47(2) · Regulation 47(3) · Regulation 27(1)(b) · Regulation 27(2) · Regulation 27(3) · Regulation 27(4) · Regulation 28(1)(b) · Regulation 28(1)(e) · Regulation 28(2) · Regulation 28(3) · Regulation 28(4) · Regulation 28(5) · Regulation 29(5) · Regulation 53(5) · Regulation 5 · official text

A tender needs time to be prepared, and the minimum time limits of the Regulations are the least a contracting authority may give. This guide starts with the general duty to set adequate time limits, then gives the minimum for each procedure, the cases in which a minimum may be shortened, and the cases in which a time limit must be extended. It ends with the standstill period, which comes from the Remedies Regulations. The time limits table lists each time limit with the provision it is read from, and its calculator counts one from a date. The text described is S.I. No. 284 of 2016 as amended by S.I. No. 203 of 2017, the only amending instrument the Irish Statute Book’s Legislation Directory lists.

Setting the time limit

The minimums are a floor, not a target. Without prejudice to the minimum time limits of Regulations 27 to 31, a contracting authority fixing the time limits for tenders and requests to participate must take account of the complexity of the contract and the time required for drawing up tenders (Regulation 47(1)).

Where tenders can be made only after a visit to the site or an on-the-spot inspection of documents supporting the procurement documents, the time limits must be longer than the minimums and fixed so that all operators concerned can be aware of all the information needed to produce tenders (Regulation 47(2)).

The minimum time limits

The minimums are counted from the date on which the contract notice, the invitation to confirm interest or the invitation to tender was sent.

ProcedureRequests to participateTenders
Open procedureNot applicable35 days from the contract notice (Regulation 27(1)(b))
Restricted procedure30 days from the contract notice or invitation to confirm interest (Regulation 28(1)(b))30 days from the invitation to tender (Regulation 28(1)(e))
Competitive procedure with negotiation30 days from the contract notice or invitation to confirm interest (Regulation 29(4))30 days from the invitation, for initial tenders, subject to Regulation 28(2) to (5) (Regulation 29(5))
Competitive dialogue30 days from the contract notice (Regulation 30(1)(b))No minimum set in Regulation 30
Innovation partnership30 days from the contract notice (Regulation 31(1)(e))No minimum set in Regulation 31
Dynamic purchasing system30 days from the contract notice or invitation to confirm interest (Regulation 34(9)(a))Not less than 10 days from the invitation to tender (Regulation 34(9)(b))

For the competitive dialogue and the innovation partnership the general duty of Regulation 47(1) still applies, and the invitation to tender must give the deadline for receipt of tenders (Schedule 6, paragraph 1(b)). The procedures themselves are explained in the guide on procedures.

Shortening a time limit

After a prior information notice

A contracting authority that published a prior information notice not itself used as a call for competition may shorten the time limit for tenders:

  • in the open procedure, to 15 days, where the notice included all the information required by Part 2 of Schedule 3 insofar as it was available when published, and was sent for publication between 35 days and 12 months before the contract notice was sent (Regulation 27(2));
  • in the restricted procedure, to 10 days, where the notice included the information in paragraphs 1 to 11 of Part 2 of Schedule 3 insofar as it was available, and was sent for publication within the same window (Regulation 28(2)).

The second reduction also applies to initial tenders in the competitive procedure with negotiation, because Regulation 29(5) applies Regulation 28(2) to (5).

Sub-central contracting authorities

In the restricted procedure, a sub-central contracting authority may set the time limit for tenders by mutual agreement with the selected candidates, provided all of them have the same time to prepare and submit their tenders (Regulation 28(3)(a)). Without agreement, the time limit may not be less than 10 days from the invitation to tender (Regulation 28(3)(b)). The same rule reaches the competitive procedure with negotiation through Regulation 29(5) and, where appropriate, a dynamic purchasing system (Regulation 34(10)).

Electronic submission

The authority may reduce by 5 days the time limit for tenders where it accepts that tenders may be submitted by electronic means in accordance with Regulation 22(1) to (6), (10) and (11): in the open procedure, from 35 to 30 days (Regulation 27(4)); in the restricted procedure, from 30 to 25 days (Regulation 28(4)).

Neither S.I. No. 284 of 2016 nor Directive 2014/24/EU says whether these reductions may be combined. Each is worded against the standard period: the electronic reduction is a reduction of the time limit in Regulation 27(1)(b) or Regulation 28(1)(e), not of a period already shortened by a prior information notice. The earlier Directive 2004/18/EC said expressly that its two electronic reductions “may be added” (Article 38(6)); the 2014 Directive has no such sentence. The cautious course is not to stack them, and the time limits table shows each separately.

Urgency: the accelerated procedure

Where a state of urgency duly substantiated by the contracting authority renders the normal time limits impracticable, it may fix shorter ones:

  • in the open procedure, a time limit for tenders of not less than 15 days from the contract notice (Regulation 27(3));
  • in the restricted procedure, not less than 15 days for requests to participate from the contract notice and not less than 10 days for tenders from the invitation to tender (Regulation 28(5)).

A procedure in which these powers are used, including a competitive procedure with negotiation using Regulation 28(5), is an accelerated procedure (Regulation 2(1)). Where appropriate, the contract notice gives the reasons for using it (Schedule 3, Part 3, paragraph 12). Urgency must be substantiated, not merely asserted. Where even these time limits cannot be met because of extreme urgency caused by unforeseeable events not attributable to the authority, the negotiated procedure without prior publication may be available (Regulation 32(2)(c)).

Extending a time limit

Late additional information and significant changes

Where it has been requested in good time, the authority must supply additional information on the specifications and supporting documents to all tenderers no later than 6 days before the time limit for tenders (Regulation 53(6)), or 4 days in an accelerated procedure (Regulation 53(7)).

The authority must extend the time limit for tenders, so that all operators concerned may be aware of all the information needed to produce tenders, where (Regulation 47(3)):

  • additional information requested in good time is not supplied, for whatever reason, at the latest 6 days before the time limit (Regulation 47(3)(a)), or 4 days in an accelerated procedure (Regulation 47(5));
  • significant changes are made to the procurement documents (Regulation 47(3)(b)).

The length of the extension must be proportionate to the importance of the information or change (Regulation 47(4)). No extension is required where the information was not requested in good time, or where its importance for preparing responsive tenders is insignificant (Regulation 47(6)).

Documents not available electronically

As a rule, procurement documents must be available by electronic means, free of charge and with unrestricted and full direct access, from the date of the notice or invitation to confirm interest (Regulation 53(1)). Where that cannot be offered for certain documents, because of one of the reasons in Regulation 22(3) or because the authority is protecting confidential information under Regulation 21(3) (Regulation 53(3), Regulation 53(4)), the time limit for tenders must be extended by 5 days, except in cases of duly substantiated urgency under Regulations 27(3) and 28(5) (Regulation 53(5)).

Questions to ask before fixing the date

  1. Do the Regulations apply? Check the estimated value, net of VAT, against the thresholds of Regulation 5; see the thresholds.
  2. Which procedure, and which minimum applies to each stage?
  3. Is the contract complex, or does it need a site visit? Then the minimum is not enough (Regulation 47(1), Regulation 47(2)).
  4. Is a reduction available, and are its conditions documented?
  5. Are all procurement documents available electronically from the start? If not, add 5 days (Regulation 53(5)).
  6. Is there time to answer questions at least 6 days before the deadline (Regulation 53(6))?

The standstill period

The standstill period before the contract is concluded is not in S.I. No. 284 of 2016 but in the Remedies Regulations (S.I. No. 130 of 2010). Regulation 5(1) of S.I. No. 130 of 2010 forbids the contracting authority to conclude the contract within the standstill period. Under Regulation 5(3) the period begins on the day after the day on which each tenderer and candidate concerned is sent notice of the outcome, and under Regulation 5(4) it lasts at least 14 calendar days where that notice is sent by fax or electronic means, or 16 calendar days where it is sent by other means. Regulation 5(2) lists contracts for which there is no standstill period, such as contracts for which no prior publication of a contract notice in the Official Journal is required.

S.I. No. 130 of 2010 is described here as amended by S.I. No. 192 of 2015 and S.I. No. 327 of 2017, which re-pointed it from the revoked 2006 Regulations to S.I. No. 284 of 2016; neither changed the standstill period. The guide on award and standstill explains the notice that starts the period, and the time limits table quotes the provision.