Time limits

Time limits in national public procurement

The time limits of the Public Authority Contracts Regulations 2016 for tenders, notices and review, each with the provision it is read from, and a calculator that counts one of them from a date.

Updated 19 November 2026Draft – awaiting legal review

Count a time limit

Choose a time limit and the date of the fact it runs from. The count shows the first day, the last day counted and where the period ends.

A draft aid, not legal advice: the counting rule has not been reviewed by a lawyer. Check the date against the provision and the facts of your procedure.

How the days are counted here

  • The day of the fact (the publication, the dispatch, the notice) does not count: the period starts on the next day.
  • Saturdays, Sundays and public holidays count, unless the provision speaks of working days.
  • A period that ends on a Saturday, a Sunday or a public holiday ends on the next working day.

This is the rule of Regulation (EEC, Euratom) No 1182/71, which Directive 2014/24/EU applies to its own time limits (recital 106). S.I. No. 284 of 2016 has no counting rule of its own: it defines only the working day (not a Saturday, Sunday, Good Friday or a Bank Holiday). The Interpretation Act 2005 would count the day a period is reckoned from (section 18(h)) and does not move an end that falls on a non-working day, so for a period counted from an event it may give a day or more less than the rule used here, never more. The standstill period of S.I. No. 130 of 2010 begins on the day after the notice by its own words (Regulation 5(3)). The site uses the Directive’s rule for every period because it is the cautious one; this choice has not yet been reviewed by a lawyer.

Tenders and requests to participate

Time limitWhatCounted fromLegal basis
35 daysminimumReceipt of tenders, open procedurethe contract notice is sentRegulation 27(1)(b)
15 daysminimumReceipt of tenders, open procedure, after a prior information noticethe contract notice is sentRegulation 27(2)
15 daysminimumReceipt of tenders, open procedure, in a duly substantiated urgencythe contract notice is sentRegulation 27(3)
5 daysreductionReduction where tenders may be submitted by electronic means, open procedure—Regulation 27(4)
30 daysminimumReceipt of requests to participate, restricted procedurethe contract notice is sentRegulation 28(1)(b)
30 daysminimumReceipt of tenders, restricted procedurethe invitation to tender is sentRegulation 28(1)(e)
10 daysminimumReceipt of tenders, restricted procedure, after a prior information noticethe invitation to tender is sentRegulation 28(2)
10 daysminimumReceipt of tenders, restricted procedure, sub-central authority without agreement on the time limitthe invitation to tender is sentRegulation 28(3)(b)
5 daysreductionReduction where tenders may be submitted by electronic means, restricted procedure—Regulation 28(4)
15 daysminimumReceipt of requests to participate, restricted procedure, in urgencythe contract notice is sentRegulation 28(5)(a)
10 daysminimumReceipt of tenders, restricted procedure, in urgencythe invitation to tender is sentRegulation 28(5)(b)
30 daysminimumReceipt of requests to participate, competitive procedure with negotiationthe contract notice is sentRegulation 29(4)
30 daysminimumReceipt of initial tenders, competitive procedure with negotiationthe invitation is sentRegulation 29(5)
30 daysminimumReceipt of requests to participate, competitive dialoguethe contract notice is sentRegulation 30(1)(b)
30 daysminimumReceipt of requests to participate, innovation partnershipthe contract notice is sentRegulation 31(1)(e)
30 daysminimumReceipt of requests to participate, dynamic purchasing systemthe contract notice is sentRegulation 34(9)(a)
10 daysminimumReceipt of tenders, dynamic purchasing systemthe invitation to tender is sentRegulation 34(9)(b)

Information and notices

Time limitWhatCounted fromLegal basis
6 daysminimumLast day to supply additional information requested in good timethe time limit for the receipt of tendersRegulation 53(6)
4 daysminimumLast day to supply additional information, accelerated procedurethe time limit for the receipt of tendersRegulation 53(7)
30 daysmaximumSending the contract award noticethe award of the contractRegulation 50(1)
15 daysmaximumInforming a candidate or tenderer who asks in writingthe receipt of a request in writingRegulation 55(2)

Review

Time limitWhatCounted fromLegal basis
14 calendar daysminimumStandstill period before the contract is concluded (notice sent electronically)the notice of the outcome is sent by electronic meansS.I. 130/2010 Regulation 5(4)(a)
16 calendar daysminimumStandstill period before the contract is concluded (notice sent by other means)the notice of the outcome is sent by other meansS.I. 130/2010 Regulation 5(4)(b)

Public holidays in 2026

The public holidays of the Organisation of Working Time Act 1997, and Good Friday, which S.I. No. 284 of 2016 does not count as a working day.

  • 1 January 2026New Year's Day
  • 2 February 2026St Brigid's Day
  • 17 March 2026St Patrick's Day
  • 3 April 2026Good Friday
  • 6 April 2026Easter Monday
  • 4 May 2026May Bank Holiday
  • 1 June 2026June Bank Holiday
  • 3 August 2026August Bank Holiday
  • 26 October 2026October Bank Holiday
  • 25 December 2026Christmas Day
  • 26 December 2026St Stephen's Day