S.I. No. 284 of 2016 · Part 2 · Rules on public contracts

Regulation 28. Restricted procedure

Chapter 1 — Procedures

Text in operation from 18 April 2016, as amended by the instruments the Irish Statute Book’s Legislation Directory lists. Where this page and the official publication differ, the official publication prevails: official text

(1) In a restricted procedure—

(a) an economic operator may submit a request to participate in response to a call for competition containing the information specified in Parts 2 or 3 of Schedule 3, as the case may be, by providing the information for qualitative selection that is requested by the contracting authority,

(b) the minimum time limit for the receipt of requests to participate shall be 30 days from the date on which the contract notice or, where a prior information notice is used as a means of calling for competition, the invitation to confirm interest, is sent,

(c) only those economic operators invited to do so by the contracting authority following its assessment of the information provided may submit a tender,

(d) a contracting authority may limit the number of suitable candidates to be invited to participate in the procedure in accordance with Regulation 65, and

(e) the minimum time limit for the receipt of tenders shall be 30 days from the date on which the invitation to tender was sent.

(2) Where a contracting authority has published a prior information notice which was not itself used as a means of calling for competition, the minimum time limit for the receipt of tenders specified in paragraph (1)(e) may be shortened to 10 days, where both of the following conditions are fulfilled—

(a) the prior information notice included all the information required in paragraphs 1 to 11 of Part 2 of Schedule 3, insofar as that information was available at the time the prior information notice was published, and

(b) the prior information notice was sent for publication between 35 days and 12 months before the date on which the contract notice was sent.

(3)

(a) A sub-central contracting authority, or specific categories of sub-central contracting authorities, may set the time limit for the receipt of tenders by mutual agreement between the contracting authority and the selected candidates, where all selected candidates have the same time to prepare and submit their tenders.

(b) In the absence of an agreement on the time limit referred to in subparagraph (a), the time limit shall be not less than 10 days from the date on which the invitation to tender was sent.

(4) The time limit for receipt of tenders provided for by paragraph (1)(e) may be reduced by 5 days where the contracting authority accepts that tenders may be submitted by electronic means in accordance with Regulation 22(1) to (6), (10) and (11).

(5) Where a state of urgency duly substantiated by the contracting authority renders impracticable the time limits specified in this Regulation, the authority may fix:

(a) a time limit for the receipt of requests to participate which shall not be less than 15 days from the date on which the contract notice was sent;

(b) a time limit for the receipt of tenders which shall not be less than 10 days from the date on which the invitation to tender was sent.

Cross-references

This regulation refers to

Referred to by

Schedules it refers to