S.I. No. 284 of 2016 · Part 2 · Rules on public contracts
Regulation 32. Use of the negotiated procedure without prior publication
Chapter 1 — Procedures
(1) A contracting authority may award public contracts by a negotiated procedure without prior publication in accordance with this Regulation.
(2) A negotiated procedure without prior publication may only be used for public works contracts, public supply contracts and public service contracts in any of the following cases:
(a) where no tenders or no suitable tenders or no requests to participate or no suitable requests to participate have been submitted in response to an open procedure or a restricted procedure, where the initial conditions of the contract are not substantially altered and a report is sent to the Commission where it so requests;
(b) where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons:
(i) the purpose of the procurement is the creation or acquisition of a unique work of art or artistic performance;
(ii) competition is absent for technical reasons;
(iii) the protection of exclusive rights, including intellectual property rights;
(c) insofar as is strictly necessary where, for reasons of extreme urgency not attributable to the contracting authority and brought about by events unforeseeable by the contracting authority, the time limits specified for the open procedures or restricted procedures or competitive procedures with negotiation cannot be complied with.
(3) Paragraphs (2)(b)(ii) and (iii) apply only where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement.
(4) For the purposes of paragraph (2)(a)—
(a) a tender shall be considered not to be suitable where it is irrelevant to the contract, being manifestly incapable, without substantial changes, of meeting the contracting authority’s needs and requirements as specified in the procurement documents;
(b) a request for participation shall be considered not to be suitable where the economic operator concerned—
(i) is to be or may be excluded pursuant to Regulation 57, or
(ii) does not meet the selection criteria specified by the contracting authority pursuant to Regulation 58.
(5) A negotiated procedure without prior publication may be used for public supply contracts:
(a) where the products involved are manufactured purely for the purpose of research, experimentation, study or development, but contracts awarded pursuant to this subparagraph shall not include quantity production to establish commercial viability or to recover research and development costs;
(b) for additional deliveries by the original supplier which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance;
(c) for supplies quoted and purchased on a commodity market;
(d) for the purchase of supplies or services on particularly advantageous terms, from a supplier which is definitively winding up its business activities, or the liquidator in an insolvency procedure, an arrangement with creditors, or a similar procedure under the laws of the State.
(6) Where subparagraph (b) of paragraph (5) applies, the duration of the contract referred to in that subparagraph, as well as that of recurrent contracts shall not, as a general rule, exceed 3 years.
(7) A negotiated procedure without prior publication may be used for public service contracts where the contract concerned—
(a) follows a design contest organised in accordance with these Regulations, and
(8) Where paragraph (7)(b)(ii) applies, all winners shall be invited to participate in the negotiations.
(9) The negotiated procedure without prior publication may be used for new works or services consisting of repetition of similar works or services entrusted to the economic operator to which the same contracting authority awarded an original contract, where such works or services are in conformity with a basic project for which the original contract was awarded pursuant to a procedure in accordance with Regulation 26(1).
(10) The basic project referred to in paragraph (9) shall indicate the extent of possible additional works or services and the conditions under which they will be awarded.
(11) Where paragraph (9) applies—
(a) the possible use of the procedure referred to in that paragraph shall be disclosed as soon as the first project is put up for tender, and
(b) the total estimated cost of subsequent works or services shall be taken into consideration by the contracting authority when it applies Regulation 5.
(12) The procedure referred to in paragraph (9) may be used only during the 3 years immediately following the conclusion of the original contract.