(1) Without prejudice to the minimum time limits specified in Regulations 27 to 31, when fixing the time limits for the receipt of tenders and requests to participate, a contracting authority shall take account of the complexity of the contract and the time required for drawing up tenders.

(2) Where tenders can be made only after a visit to the site or after on-the-spot inspection of the documents supporting the procurement documents, the time limits for the receipt of tenders, which shall be longer than the minimum time limits specified in Regulations 27 to 31, shall be fixed so that all economic operators concerned may be aware of all the information necessary to produce tenders.

(3) A contracting authority shall extend the time limits for the receipt of tenders so that all economic operators concerned may be aware of all the information needed to produce tenders in the following cases:

(a) where, for whatever reason, additional information, although requested by the economic operator in good time, is not supplied at the latest 6 days before the time limit fixed for the receipt of tenders;

(b) where significant changes are made to the procurement documents.

(4) The length of the extension under paragraph (3) shall be proportionate to the importance of the information or change.

(5) In the event of an accelerated procedure referred to in Regulations 27(3) and 28(5), that period shall be 4 days.

(6) A contracting authority is not required to extend the time limits under this Regulation where—

(a) additional information has not been requested in good time, or

(b) the importance of the additional information concerned with a view to preparing responsive tenders is insignificant.

Cross-references

This regulation refers to

Want your tender documents checked before publication? We will show you how Procurelex Check does it.

Request a demo

General information on the Public Authority Contracts Regulations 2016 in force. Not legal advice.