Regulation 69. Abnormally low tenders

Chapter 3 — Conduct of the procedure · Choice of participants and award of contracts

Text in operation from 18 April 2016, as amended by the instruments the Irish Statute Book’s Legislation Directory lists. Where this page and the official publication differ, the official publication prevails: official text

(1) A contracting authority shall require economic operators to explain the price or costs proposed in a tender which appears to be abnormally low in relation to the works, supplies or services.

(2) The explanations given in accordance with paragraph (1) may relate to, amongst other things, the following:

(a) the economics of the manufacturing process, of the services provided or of the construction method;

(b) the technical solutions chosen or any exceptionally favourable conditions available to the tenderer for the supply of the products or services or for the execution of the work;

(c) the originality of the work, supplies or services proposed by the tenderer;

(d) compliance with applicable obligations referred to in Regulation 18(4);

(e) compliance with obligations referred to in Regulation 71;

(f) the possibility of the tenderer obtaining State aid.

(3) The contracting authority shall assess the information provided under this Regulation by consulting the tenderer.

(4) A contracting authority may only reject a tender where the evidence supplied under this Regulation does not satisfactorily account for the low level of price or costs proposed, taking into account the elements referred to in paragraph (2).

(5) A contracting authority shall reject a tender where it has established that the tender is abnormally low because it does not comply with applicable obligations referred to in Regulation 18(4).

(6) Where a contracting authority establishes that a tender is abnormally low because the tenderer has obtained State aid, the tender may be rejected on that ground alone only—

(a) after consultation with the tenderer concerned, and

(b) where the tenderer is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 of the TFEU.

(7) Where a contracting authority rejects a tender in the circumstances referred to in paragraph (6), it shall inform the Commission in writing.

Cross-references

This regulation refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Check does it.

Request a demo

General information on the Public Authority Contracts Regulations 2016 in force. Not legal advice.