S.I. No. 284 of 2016 · Part 2 · Rules on public contracts

Regulation 71. Subcontracting

Chapter 4 — Contract performance

Text in operation from 18 April 2016, as amended by the instruments the Irish Statute Book’s Legislation Directory lists. Where this page and the official publication differ, the official publication prevails: official text

(1) In procurement documents, a contracting authority may ask a tenderer to indicate, in its tender, any share of the contract that it may intend to subcontract to third parties and any proposed subcontractors.

(2) Paragraph (1) is without prejudice to the main contractor’s liability.

(3) In the case of works contracts and in respect of services to be provided at a facility under the direct oversight of the contracting authority, after the award of the contract and no later than when the performance of the contract commences, the contracting authority shall require the main contractor to indicate to the contracting authority the name, contact details and legal representatives of its subcontractors, involved in such works or services, in so far as known at the relevant time.

(4) A contracting authority shall require the main contractor to notify the contracting authority of—

(a) any changes to the information notified during the course of the contract, and

(b) the name, contact details and legal representatives of any new subcontractors which the main contractor subsequently involves in such works or services.

(5) Where necessary for the purposes of paragraph (8), the required information shall be accompanied by the subcontractors’ self-declarations as provided for in Regulation 59 and subcontractors which are presented after the award of the contract shall provide the certificates and other supporting documents instead of the self-declaration.

(6) Paragraphs (3) and (4) do not apply to suppliers.

(7) Where a contracting authority determines that such compliance in the following cases or by the following persons is required (and makes it a requirement accordingly), the obligations provided for in paragraphs (3) and (4) shall also fall to be complied with in such cases or by such persons as it determines, including, but not limited to—

(a) cases of supply contracts, services contracts, other than those concerning services to be provided at the facilities under the direct oversight of the contracting authority, or to suppliers involved in works or services contracts, and

(b) subcontractors of the main contractor’s subcontractors or subcontractors further down the subcontracting chain.

(8) To avoid contraventions of the obligations referred to in Regulation 18(4), a contracting authority may take appropriate measures by, amongst other things, verifying in accordance with Regulations 59, 60 and 61, whether there are grounds for exclusion of subcontractors under Regulation 57.

(9) In the case of verification under paragraph (8), the contracting authority—

(a) shall require that an economic operator replaces a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion, or

(b) may require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.

Cross-references

This regulation refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Check does it.

Request a demo

General information on the Public Authority Contracts Regulations 2016 in force. Not legal advice.