FAQ
Procedures
Which award procedure a contracting authority may use, when negotiation or dialogue is allowed, and when a contract may be awarded without a call for competition.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
These answers are on S.I. No. 284 of 2016, as amended by S.I. No. 203 of 2017.
When may the competitive procedure with negotiation or the competitive dialogue be used?
Where the needs cannot be met without adapting readily available solutions, the contract includes design or innovative solutions, it cannot be awarded without prior negotiation because of its nature, complexity, legal and financial make-up or risks, or the technical specifications cannot be set precisely enough by reference to a standard or similar (Regulation 26(3)(a)). They may also be used where an open or restricted procedure produced only irregular or unacceptable tenders (Regulation 26(3)(b)).
Legal basisRegulation 26(3)(a) · Regulation 26(3)(b) · official text
What is the difference between an irregular and an unacceptable tender?
A tender is irregular if it does not comply with the procurement documents, was received late, shows evidence of collusion or corruption, or has been found to be abnormally low (Regulation 26(5)). It is unacceptable if the tenderer lacks the required qualifications or the price exceeds the authority’s budget as determined and documented before the procedure was launched (Regulation 26(6)).
Legal basisRegulation 26(5) · Regulation 26(6) · official text
What may and may not be negotiated in a competitive procedure with negotiation?
The authority negotiates the initial and later tenders, but not the final tenders, to improve their content (Regulation 29(8)). The minimum requirements and the award criteria are not negotiable (Regulation 29(9)). It may award on the initial tenders without negotiation if it reserved that possibility in the contract notice or invitation to confirm interest (Regulation 29(10)).
Legal basisRegulation 29(8) · Regulation 29(9) · Regulation 29(10) · official text
How is a contract awarded after a competitive dialogue?
On the sole basis of the best price-quality ratio (Regulation 30(1)(e)). When the dialogue is concluded, the remaining participants submit final tenders based on the solutions identified (Regulation 30(4)(a)), which are assessed on the award criteria in the contract notice or descriptive document (Regulation 30(5)(a)).
Legal basisRegulation 30(1)(e) · Regulation 30(4)(a) · Regulation 30(5)(a) · official text
When is an innovation partnership the right procedure?
When the authority needs an innovative product, service or works that cannot be met by purchasing what is already available on the market (Regulation 31(1)(b)(i)). The partnership develops the solution and then purchases it if it meets the agreed performance levels and maximum costs (Regulation 31(2)).
Legal basisRegulation 31(1)(b)(i) · Regulation 31(2) · official text
When may a contract be awarded without publishing a call for competition?
Only in the cases of Regulation 32 (Regulation 26(10)): for example, no suitable tenders in an open or restricted procedure, only one operator able to supply, or extreme urgency caused by unforeseeable events (Regulation 32(2)), plus some cases for supplies, design contests and repeat works or services. The guide on the negotiated procedure without prior publication lists every ground.
Legal basisRegulation 26(10) · Regulation 32(2) · official text
Related pages
Want your tender documents checked before publication? We will show you how Procurelex Check does it.
Request a demoGeneral information on the Public Authority Contracts Regulations 2016 in force. Not legal advice.