S.I. No. 284 of 2016 · Part 2 · Rules on public contracts
Regulation 72. Modification of contracts during their term
Chapter 4 — Contract performance
(1) Contracts and framework agreements, including contracts awarded in accordance with Regulation 74, may be modified without a new procurement procedure in accordance with these Regulations in any of the following cases:
(a) where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses or options, where such clauses—
(i) state the scope and nature of possible modifications or options as well as the conditions under which they may be used, and
(ii) do not provide for modifications or options that would alter the overall nature of the contract or the framework agreement;
(b) for additional works, services or supplies by the original contractor, irrespective of their value, that have become necessary and were not included in the initial procurement where a change of contractor—
(i) cannot be made for economic or technical reasons, including requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement, and
(ii) would cause significant inconvenience or substantial duplication of costs for the contracting authority;
(c) where the following conditions are fulfilled:
(i) the need for modification has been brought about by circumstances which a diligent contracting authority could not have foreseen;
(ii) the modification does not alter the overall nature of the contract;
(d) where a new contractor replaces the contractor to which the contracting authority had initially awarded the contract as a consequence of—
(i) an unequivocal review clause or option in conformity with subparagraph (a), or
(ii) universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established, where this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of these Regulations;
(e) where the modifications, irrespective of their value, are not substantial within the meaning of paragraph (7).
(a) Notwithstanding paragraph (1)(b)—
(i) any increase in price shall not exceed 50% of the value of the original contract,
(ii) where several successive modifications are made, that limitation shall apply to the value of each modification, and
(iii) consecutive modifications referred to in clause (ii) shall not be aimed at circumventing these Regulations.
(b) Notwithstanding paragraph (1)(c)—
(i) any increase in price shall not exceed 50% of the value of the original contract or framework agreement,
(ii) where several successive modifications are made, that limitation shall apply to the value of each modification, and
(iii) consecutive modifications referred to in clause (ii) shall not be aimed at circumventing these Regulations.
(3) A contracting authority which has modified a contract in either of the cases described in paragraph (1)(b) or (c) shall publish a notice to that effect, in the Official Journal and that notice shall—
(a) contain the information specified in Part 7 of Schedule 3, and
(b) be published in accordance with Regulation 51.
(4) Furthermore and without any need to verify that the conditions set out under paragraph (7)(a) to (d) are met, contracts may equally be modified without a new procurement procedure in accordance with these Regulations being necessary where the value of the modifications is below each of the following values:
(a) the thresholds specified in Regulation 5;
(b) 10 per cent of the initial contract value for service and supply contracts or 15 per cent of the initial contract value for works contracts.
(5) For the purposes of paragraph (4) the modification may not alter the overall nature of the contract or framework agreement and where several successive modifications are made, the value shall be assessed on the basis of the net cumulative value of the successive modifications.
(6) For the purpose of the calculation of the value referred to in paragraph (4)(b), the updated value shall be the reference value when the contract includes an indexation clause.
(7) A modification of a contract or framework agreement during its term shall be considered substantial for the purposes of paragraph (1)(e) where the modification renders the contract or framework agreement, as the case may be, materially different in character from the contract or framework agreement initially concluded, and, in any event, without prejudice to paragraphs (1) to (5) a modification shall be considered to be substantial where one or more of the following conditions is met:
(a) the modification introduces conditions which, had they been part of the initial procurement procedure, would have—
(i) allowed for the admission of other candidates than those initially selected,
(ii) allowed for the acceptance of a tender other than that originally accepted, or
(iii) attracted additional participants in the procurement procedure;
(b) the modification changes the economic balance of the contract or framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;
(c) the modification extends the scope of the contract or framework agreement considerably;
(d) a new contractor replaces the one to which the contracting authority had initially awarded the contract in cases other than those specified in paragraph (1)(d).
(8) A new procurement procedure in accordance with these Regulations shall be required for other modifications of the provisions of a public contract or a framework agreement during its term in circumstances other than those provided for in paragraphs (1) to (5).
Amended byS.I. No. 203 of 2017