S.I. No. 284 of 2016 · Part 5 · Revocation and transitional provisions
Regulation 86. Transitional provisions
(1) Subject to paragraph (4), these Regulations do not apply to—
(a) a contract award procedure, or
(b) a design contest, commenced by a contracting authority before 18 April 2016.
(2) For the purposes of paragraph (1), a contract award procedure or design contest has been commenced by a contracting authority before 18 April 2016 if, before that date—
(a) the contracting authority has sent a notice to the Publications Office in accordance with the Regulations of 2006 in order to invite tenders or requests to be selected to tender for, or to negotiate in respect of, a proposed public contract or framework agreement,
(b) the contracting authority has published any form of advertisement seeking offers or expressions of interest in a proposed public contract or framework agreement,
(c) the contracting authority has contacted any economic operator in order to—
(i) seek expressions of interest or offers in respect of a proposed public contract or framework agreement, or
(ii) respond to an unsolicited expression of interest or offer received from that economic operator in relation to a proposed public contract or framework agreement, or
(d) the contracting authority has sent a notice to the Official Journal in accordance with the Regulations of 2006 in order to publicise its intention to hold a design contest.
(3) Subject to paragraph (4), these Regulations do not apply to the award of a specific contract based on a framework agreement where the framework agreement was concluded—
(a) before 18 April 2016, or
(b) on or after 18 April 2016 following a contract award procedure to which these Regulations, by virtue of paragraph (1), do not apply.
(4) Regulation 72 applies, and Regulation 32(1)(d) and (5)(e) of the Regulations of 2006 do not apply, to a contract or framework agreement to which these Regulations would otherwise not apply by virtue of paragraph (1) or (3).
(5) In this regulation, “contracting authority”, “design contest”, “framework agreement” and “public contract” have the same meanings, respectively, as in the Regulations of 2006.