Practical guide
Division into lots
When a contracting authority may divide a contract into lots, why it must explain a decision not to, how it may limit the lots one tenderer can win, and when it may award several lots together.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
Legal basisRegulation 46(1) · Regulation 46(2) · Regulation 46(3) · Regulation 46(4) · Regulation 46(5) · Regulation 46(6) · Regulation 6(11)(a) · Regulation 6(13) · Regulation 58(12) · Regulation 58(13) · official text
Dividing a contract into lots breaks one requirement into parts that can be tendered for and awarded separately, which can open it to economic operators unable to perform the whole. Regulation 46 leaves the decision to divide with the authority but asks it to explain a decision not to divide, and it sets the rules for how many lots a tenderer may bid for or win and for awarding several lots together. Other provisions decide how lots count towards the thresholds and how selection criteria apply to them.
The decision to divide
A contracting authority may decide to award a contract in the form of separate lots, and may determine the size and subject matter of those lots (Regulation 46(1)). The Regulations do not oblige it to divide, and they do not prescribe how the lots are drawn up.
What the Regulations do require is an explanation where the authority decides not to divide. It must provide an indication of the main reasons for that decision, either in the procurement documents or in the written report on the procedure under Regulation 84(1) (Regulation 46(2)). The contract notice has a matching item: where the contract is not subdivided into lots, the notice indicates the reasons, unless this information is provided in the individual report (Schedule 3).
The general principles apply to the design of the lots as to everything else. Economic operators must be treated equally and without discrimination, and the authority must act in a transparent and proportionate manner (Regulation 18(1)). A procurement may not be designed with the intention of artificially narrowing competition, which happens where the design is made with the intention of unduly favouring or disadvantaging certain economic operators (Regulation 18(2), Regulation 18(3)).
Lots and the thresholds
Dividing a contract into lots does not take it outside the Regulations. A procurement must not be subdivided with the effect of preventing it from falling within their scope, other than where the subdivision is justified by objective reasons (Regulation 6(6)).
When the value is estimated:
- for works or services that may result in contracts awarded in separate lots, the total estimated value of all the lots is taken into account (Regulation 6(11)(a)); where that aggregate value reaches the relevant threshold, the Regulations apply to the award of each lot (Regulation 6(11)(b));
- for similar supplies that may be awarded in separate lots, the same aggregation applies for the supply thresholds (Regulation 6(12)(a), Regulation 6(12)(b)).
There is one exception for small lots. An authority may award individual lots without applying the procedures of the Regulations where the estimated value of the lot, net of VAT, is below the amount set for supplies or services or for works, and the aggregate value of the lots so awarded does not exceed 20% of the aggregate value of all the lots (Regulation 6(13)). The amounts and the current thresholds should be checked against later revisions before relying on them; the guide on thresholds and estimated value explains the calculation.
What the notice must say
Lots are announced in the call for competition. The authority must indicate, in the contract notice or in the invitation to confirm interest, whether tenders may be submitted for one, for several or for all of the lots (Regulation 46(3)).
The contract notice also gives, where the contract is divided into lots, the CPV codes, the place of performance, the description of the procurement and the estimated order of magnitude for each lot, together with any limit on the number of lots that may be awarded to one tenderer (Schedule 3). See the guide on notices and procurement documents.
Limiting the lots one tenderer can win
Three separate questions arise, and each is settled in a set place.
| Limit | Where it is set | Provision |
|---|---|---|
| On the lots a tenderer may bid for (one, several or all) | Contract notice or invitation to confirm interest | Regulation 46(3) |
| On the lots that may be awarded to one tenderer | Contract notice or invitation to confirm interest, with the maximum number stated | Regulation 46(4) |
| On how lots are allocated if a tenderer would win more than the maximum | Procurement documents | Regulation 46(5) |
Where tenders may be submitted for several or all lots, the authority may limit the number of lots that may be awarded to one tenderer, but only if the maximum number of lots per tenderer is stated in the contract notice or in the invitation to confirm interest (Regulation 46(4)).
A limit on awards needs a rule for the case where the award criteria would give one tenderer more lots than the maximum. The authority must indicate in the procurement documents the objective and non-discriminatory criteria or rules it intends to apply to decide which lots that tenderer will be awarded (Regulation 46(5)). The rule has to be fixed in advance; it cannot be invented after the tenders are evaluated.
Awarding several lots together
Where more than one lot may be awarded to the same tenderer, the authority may award a contract combining several or all lots (Regulation 46(6)). It may do so only where it has specified, in the contract notice or in the invitation to confirm interest:
- that it reserves the possibility of doing so, and
- the lots or groups of lots that may be combined.
Without that reservation in the notice, each lot is awarded separately.
Selection criteria for each lot
Where a contract is divided into lots, the selection criteria of Regulation 58 apply in relation to each individual lot (Regulation 58(12)). This matters most for economic and financial standing: the minimum yearly turnover may not exceed twice the estimated contract value, except in duly justified cases (Regulation 58(9)), and since Regulation 58 applies lot by lot, the requirement is set for each lot.
There is one exception. The authority may set the minimum yearly turnover by reference to groups of lots, in the event that the successful tenderer is awarded several lots to be executed at the same time (Regulation 58(13)). A tenderer bidding for several lots should check whether the turnover requirement rises with the number of lots it may win. See the guide on selection criteria.
Lots and framework agreements
Lots may also be used within a framework agreement concluded with more than one economic operator. Where the framework agreement specifies all the terms governing the provision of a lot, that lot may be performed partly without and partly with a reopening of competition, if the procurement documents for the framework agreement so stipulate (Regulation 33(8)(b)), regardless of whether all the terms have been specified for the other lots (Regulation 33(10)). The guide on framework agreements and dynamic purchasing explains how contracts are awarded under a framework.
A practical sequence for the authority
- Estimate the value of the whole requirement, aggregating all lots (Regulation 6(11)(a)).
- Decide whether to divide, and the size and subject matter of the lots (Regulation 46(1)); if not dividing, record the main reasons (Regulation 46(2)).
- Decide whether tenderers may bid for one, several or all lots, and state it in the notice (Regulation 46(3)).
- If limiting awards per tenderer, state the maximum in the notice (Regulation 46(4)) and the allocation rule in the procurement documents (Regulation 46(5)).
- If combined awards are possible, reserve them and list the combinable lots in the notice (Regulation 46(6)).
- Set selection criteria lot by lot, or by groups of lots for turnover where appropriate (Regulation 58(12), Regulation 58(13)).
- Keep the documentation justifying these decisions (Regulation 84(4)).
For the tenderer
Read the notice first: it says which lots you may bid for, whether the authority caps the number of lots one tenderer can win, and whether it may combine lots into a single contract. Then read the procurement documents for the allocation rule that applies if you would otherwise win too many lots, and for the selection criteria of each lot you bid for.
Related pages
Previous guide
Technical specifications, labels and variants
Next guide
Award criteria and life-cycle costing