S.I. No. 284 of 2016 · Part 1 · Scope, definitions and general principles

Regulation 16. Mixed procurement involving defence or security aspects

Chapter 1 — Scope and definitions · Specific situations

Text in operation from 18 April 2016, as amended by the instruments the Irish Statute Book’s Legislation Directory lists. Where this page and the official publication differ, the official publication prevails: official text

(1) This Regulation applies to mixed contracts which have as their subject matter procurement to which these Regulations apply and procurement to which Article 346 of the TFEU or the Defence Contract Regulations apply.

(2) Where the different parts of a public contract to which this Regulation applies are objectively separable, a contracting authority may choose to award separate contracts for the separate parts or to award a single contract.

(3) Where a contracting authority chooses to award separate contracts for separate parts of a contract to which this Regulation applies, the decision as to which legal regime applies to any one of such separate contracts shall be taken on the basis of the characteristics of the separate part concerned.

(4) Where a contracting authority chooses to award a single contract in respect of a contract to which this Regulation applies, the following criteria shall apply to determine the applicable legal regime:

(a) where part of a contract is covered by Article 346 of the TFEU, the contract may be awarded without applying these Regulations, where the award of a single contract is justified for objective reasons;

(b) where the Defence Contract Regulations apply to part of a contract, the contract may be awarded in accordance with those Regulations, subject to any exclusions and thresholds specified in those Regulations, where the award of a single contract is justified by objective reasons;

(c) where both subparagraphs (a) and (b) would otherwise apply to a contract, the contract may be awarded without applying these Regulations where the award of a single contract is justified for objective reasons.

(5) A contracting authority shall not choose to award a contract to which this Regulation applies as a single contract where the purpose of so choosing is to exclude the award from the application of either these Regulations or the Defence Contract Regulations.

(6) Where the different parts of a contract to which this Regulation applies are objectively not separable, the contract may be awarded—

(a) without applying these Regulations where the contract includes elements to which Article 346 of the TFEU applies, and

(b) in accordance with the Defence Contract Regulations where the contract does not include elements to which Article 346 of the TFEU applies.

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Check does it.

Request a demo

General information on the Public Authority Contracts Regulations 2016 in force. Not legal advice.