The only cases in which a contracting authority may award a public contract without publishing a call for competition, the conditions attached to each, and what must be recorded and reported.

The negotiated procedure without prior publication lets a contracting authority award a public contract without first publishing a call for competition. Because it removes competition, the Regulations confine it to a closed list of cases: a contracting authority may apply it only in the cases referred to in Regulation 32 ([Regulation 26(10)](https://procurelex.ie/regulations/26#p10)), and may award public contracts by it only in accordance with that Regulation ([Regulation 32(1)](https://procurelex.ie/regulations/32#p1)). This guide takes each ground in turn, then the record the authority must keep. It describes S.I. No. 284 of 2016 as amended by S.I. No. 203 of 2017, the only amending instrument the Irish Statute Book’s Legislation Directory lists.

## The grounds at a glance

| Ground                                                                             | Contracts                 | Provision          | Main conditions                                                                                                         |
| ---------------------------------------------------------------------------------- | ------------------------- | ------------------ | ----------------------------------------------------------------------------------------------------------------------- |
| No tenders, or no suitable tenders or requests, in an open or restricted procedure | Works, supplies, services | [Regulation 32(2)(a)](https://procurelex.ie/regulations/32#p2-a)     | Initial conditions not substantially altered; report to the Commission if it requests one                               |
| Unique work of art or artistic performance                                         | Works, supplies, services | [Regulation 32(2)(b)(i)](https://procurelex.ie/regulations/32#p2-b-i)   | Only one operator can supply                                                                                            |
| Competition absent for technical reasons                                           | Works, supplies, services | [Regulation 32(2)(b)(ii)](https://procurelex.ie/regulations/32#p2-b-ii)  | No reasonable alternative; no artificial narrowing ([Regulation 32(3)](https://procurelex.ie/regulations/32#p3))                                                       |
| Exclusive rights, including intellectual property                                  | Works, supplies, services | [Regulation 32(2)(b)(iii)](https://procurelex.ie/regulations/32#p2-b-iii) | No reasonable alternative; no artificial narrowing ([Regulation 32(3)](https://procurelex.ie/regulations/32#p3))                                                       |
| Extreme urgency                                                                    | Works, supplies, services | [Regulation 32(2)(c)](https://procurelex.ie/regulations/32#p2-c)     | Strictly necessary; unforeseeable; not attributable to the authority                                                    |
| Products made purely for research, experimentation, study or development           | Supplies                  | [Regulation 32(5)(a)](https://procurelex.ie/regulations/32#p5-a)     | No quantity production for commercial viability or cost recovery                                                        |
| Additional deliveries by the original supplier                                     | Supplies                  | [Regulation 32(5)(b)](https://procurelex.ie/regulations/32#p5-b)     | Change of supplier would cause incompatibility or disproportionate difficulty; as a general rule 3 years ([Regulation 32(6)](https://procurelex.ie/regulations/32#p6)) |
| Supplies quoted and purchased on a commodity market                                | Supplies                  | [Regulation 32(5)(c)](https://procurelex.ie/regulations/32#p5-c)     | None further in the text                                                                                                |
| Particularly advantageous terms from a supplier winding up or in insolvency        | Supplies or services      | [Regulation 32(5)(d)](https://procurelex.ie/regulations/32#p5-d)     | Supplier definitively winding up, or liquidator, arrangement with creditors or similar procedure                        |
| Contract following a design contest                                                | Services                  | [Regulation 32(7)](https://procurelex.ie/regulations/32#p7)       | Awarded to the winner or one of the winners under the contest rules; all winners invited ([Regulation 32(8)](https://procurelex.ie/regulations/32#p8))                 |
| Repetition of similar works or services                                            | Works, services           | [Regulation 32(9)](https://procurelex.ie/regulations/32#p9)       | Basic project; disclosed at the first tender; within 3 years ([Regulation 32(10)](https://procurelex.ie/regulations/32#p10), [Regulation 32(11)](https://procurelex.ie/regulations/32#p11), [Regulation 32(12)](https://procurelex.ie/regulations/32#p12))              |

## Grounds open to works, supply and service contracts

### No suitable tenders or requests to participate

The procedure may be used where no tenders, no suitable tenders, no requests to participate or no suitable requests to participate have been submitted in response to an open or restricted procedure, provided the initial conditions of the contract are not substantially altered and a report is sent to the Commission where it so requests ([Regulation 32(2)(a)](https://procurelex.ie/regulations/32#p2-a)).

The text says what “not suitable” means. A tender is not suitable where it is irrelevant to the contract, being manifestly incapable, without substantial changes, of meeting the authority’s needs and requirements as specified in the procurement documents ([Regulation 32(4)(a)](https://procurelex.ie/regulations/32#p4-a)). A request to participate is not suitable where the operator is to be or may be excluded under Regulation 57, or does not meet the selection criteria set under Regulation 58 ([Regulation 32(4)(b)](https://procurelex.ie/regulations/32#p4-b)).

This ground is narrower than the one in Regulation 26 for irregular or unacceptable tenders, which leads to a competitive procedure with negotiation or a competitive dialogue rather than to this procedure ([Regulation 26(3)(b)](https://procurelex.ie/regulations/26#p3-b)); see the guide on [procedures](https://procurelex.ie/guides/procedures).

### Only one economic operator can supply

The procedure may be used where the works, supplies or services can be supplied only by a particular economic operator because the purpose is the creation or acquisition of a unique work of art or artistic performance, because competition is absent for technical reasons, or because of the protection of exclusive rights, including intellectual property rights ([Regulation 32(2)(b)](https://procurelex.ie/regulations/32#p2-b)).

The technical and exclusive-rights reasons are qualified: they apply only where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement ([Regulation 32(3)](https://procurelex.ie/regulations/32#p3)). An authority relying on them should be able to show why no alternative would do and that its own requirements did not create the exclusivity.

### Extreme urgency

The procedure may be used insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority and not attributable to it, the time limits for the open, restricted or competitive procedure with negotiation cannot be complied with ([Regulation 32(2)(c)](https://procurelex.ie/regulations/32#p2-c)).

Each element is a condition: the urgency must be extreme, the events unforeseeable, the cause not the authority’s, and the use limited to what is strictly necessary. Where urgency is real but less pressing, the shortened time limits of the [accelerated procedure](https://procurelex.ie/glossary/accelerated-procedure) may be enough ([Regulation 27(3)](https://procurelex.ie/regulations/27#p3), [Regulation 28(5)](https://procurelex.ie/regulations/28#p5)); see [time limits for tenders](https://procurelex.ie/guides/time-limits-for-tenders).

## Grounds for supply contracts

For public supply contracts the procedure may also be used ([Regulation 32(5)](https://procurelex.ie/regulations/32#p5)):

- where the products are manufactured purely for research, experimentation, study or development, but not for quantity production to establish commercial viability or to recover research and development costs ([Regulation 32(5)(a)](https://procurelex.ie/regulations/32#p5-a));
- for additional deliveries by the original supplier, intended as a partial replacement or extension of existing supplies or installations, where a change of supplier would oblige the authority to acquire supplies with different technical characteristics resulting in incompatibility or disproportionate technical difficulties in operation and maintenance ([Regulation 32(5)(b)](https://procurelex.ie/regulations/32#p5-b));
- for supplies quoted and purchased on a commodity market ([Regulation 32(5)(c)](https://procurelex.ie/regulations/32#p5-c));
- for the purchase of supplies or services on particularly advantageous terms from a supplier definitively winding up its business, or from the liquidator in an insolvency procedure, an arrangement with creditors or a similar procedure under the laws of the State ([Regulation 32(5)(d)](https://procurelex.ie/regulations/32#p5-d)).

For additional deliveries, the duration of the contract, and of recurrent contracts, must not as a general rule exceed 3 years ([Regulation 32(6)](https://procurelex.ie/regulations/32#p6)). Although paragraph (5) is introduced as applying to supply contracts, its last case speaks of “supplies or services”; how far it reaches service contracts is a point to check.

## Service contracts following a design contest

For public service contracts, the procedure may be used where the contract follows a [design contest](https://procurelex.ie/glossary/design-contests) organised in accordance with the Regulations and is to be awarded, under the contest rules, to the winner or one of the winners ([Regulation 32(7)](https://procurelex.ie/regulations/32#p7)). If there are several winners, all of them must be invited to the negotiations ([Regulation 32(8)](https://procurelex.ie/regulations/32#p8)).

The intention to award such a contract must be indicated in the contest notice ([Regulation 79(2)](https://procurelex.ie/regulations/79#p2)), and, for a design contest with prizes or payments, the estimated value of a later service contract announced in the contest notice is included when the threshold is calculated ([Regulation 78(3)](https://procurelex.ie/regulations/78#p3)).

## Repetition of similar works or services

The procedure may be used for new works or services consisting of the repetition of similar works or services entrusted to the operator that won an original contract from the same authority, where they conform to a basic project for which the original contract was awarded under a procedure in accordance with Regulation 26(1) ([Regulation 32(9)](https://procurelex.ie/regulations/32#p9)). Four conditions follow:

1. the basic project must indicate the extent of possible additional works or services and the conditions under which they will be awarded ([Regulation 32(10)](https://procurelex.ie/regulations/32#p10));
2. the possible use of this procedure must be disclosed as soon as the first project is put up for tender ([Regulation 32(11)(a)](https://procurelex.ie/regulations/32#p11-a));
3. the total estimated cost of the later works or services must be taken into account when the authority applies the thresholds of Regulation 5 ([Regulation 32(11)(b)](https://procurelex.ie/regulations/32#p11-b));
4. the procedure may be used only during the 3 years immediately following the conclusion of the original contract ([Regulation 32(12)](https://procurelex.ie/regulations/32#p12)).

The repetition must therefore be planned and announced from the start; it cannot be added after the original contract has been let.

## What must be recorded and reported

Regulation 32 itself says little about how the negotiations are run. The duties that follow from using it are mainly about justification:

- **Written report.** For every contract covered by the Regulations the authority prepares a written report which, for a negotiated procedure without prior publication, must give the circumstances referred to in Regulation 32 which justify its use ([Regulation 84(1)(f)](https://procurelex.ie/regulations/84#p1-f)). Where the Minister so requests, the report or its main elements must be sent to the Minister or to a body the Minister directs ([Regulation 84(6)](https://procurelex.ie/regulations/84#p6)).
- **Documentation.** The authority keeps documentation of the progress of the procedure, including communications with operators, internal deliberations and any negotiation, for at least 3 years from the award ([Regulation 84(4)](https://procurelex.ie/regulations/84#p4), [Regulation 84(5)](https://procurelex.ie/regulations/84#p5)).
- **Contract award notice.** A contract award notice must still be sent for publication within 30 days of the award ([Regulation 50(1)](https://procurelex.ie/regulations/50#p1)), and its content includes, for this procedure, the justification for using it ([Regulation 50(2)](https://procurelex.ie/regulations/50#p2), [Schedule 3](https://procurelex.ie/regulations/schedule-3), Part 4).
- **Report to the Commission.** Under the first ground, a report goes to the Commission where it so requests ([Regulation 32(2)(a)](https://procurelex.ie/regulations/32#p2-a)).

## Why the justification matters: remedies

Review is governed by the Remedies Regulations (S.I. No. 130 of 2010), not by S.I. No. 284 of 2016. Regulation 5(2)(a) of S.I. No. 130 of 2010 provides that there is no standstill period for a contract where S.I. No. 284 of 2016 does not require prior publication of a contract notice in the Official Journal. Regulation 11(2)(a) of S.I. No. 130 of 2010 requires the court to declare a contract ineffective where it was concluded without a contract notice when that was not permitted; Regulation 11(3) disapplies this where the authority considered the award permitted, published a notice in the Official Journal stating that it intended to conclude the contract, and did not conclude it before the end of 14 calendar days beginning on the day after that publication.

S.I. No. 130 of 2010 is described here as amended by S.I. No. 192 of 2015 and S.I. No. 327 of 2017; the 2017 amendments point it at S.I. No. 284 of 2016. The guides on [remedies](https://procurelex.ie/guides/remedies) and on [award and standstill](https://procurelex.ie/guides/award-and-standstill) cover it further.