# The European Single Procurement Document (ESPD)

- URL: https://procurelex.ie/guides/espd
- Updated 2026-11-20
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-20
- Legal basis: Regulation 59(1), Regulation 59(3), Regulation 59(4), Regulation 59(6), Regulation 59(7), Regulation 59(8), Regulation 59(9), Regulation 59(11), Regulation 59(12), Regulation 60(4), Regulation 61(1)

How the ESPD works as preliminary evidence on exclusion and selection, what it must contain, when the supporting documents are requested, and when an operator need not supply them.

Proving that it is not excluded and that it meets the selection criteria can mean many certificates for an economic operator. The [ESPD](https://procurelex.ie/glossary/espd), the European Single Procurement Document, lets it start with a self-declaration instead. The authority must accept the declaration at the time of submission; it must ask for the certificates before award from the tenderer it has chosen, and may ask for them earlier only where necessary for the proper conduct of the procedure. This guide explains Regulation 59 and how it works with the rules on means of proof (Regulation 60) and e-Certis (Regulation 61).

The text described here is S.I. No. 284 of 2016 as amended by S.I. No. 203 of 2017, the only amending instrument the Irish Statute Book’s Legislation Directory lists. Several provisions of Regulations 59 and 61 had deferred start dates, noted below.

## What the ESPD is

The ESPD is the European Single Procurement Document referred to in Regulation 59(1) ([Regulation 2(1)](https://procurelex.ie/regulations/2#p1)). At the time of submission of requests to participate or of tenders, a contracting authority shall accept the ESPD, consisting of an updated self-declaration, as preliminary evidence instead of certificates issued by public authorities or third parties ([Regulation 59(1)](https://procurelex.ie/regulations/59#p1)). It covers three things:

1. that the operator is not in a situation in which it shall or may be excluded under Regulation 57 ([Regulation 59(1)(a)](https://procurelex.ie/regulations/59#p1-a));
2. that it meets the relevant selection criteria specified under Regulation 58 ([Regulation 59(1)(b)](https://procurelex.ie/regulations/59#p1-b));
3. where applicable, that it fulfils the objective rules and criteria for reducing the number of candidates under Regulation 65 ([Regulation 59(1)(c)](https://procurelex.ie/regulations/59#p1-c)).

At that stage the Regulation leaves the authority no choice: it shall accept the ESPD instead of the certificates.

## What it contains

The ESPD is a formal statement by the operator that the relevant grounds for exclusion do not apply or that the relevant selection criterion is fulfilled, and it provides the relevant information required by the authority ([Regulation 59(3)](https://procurelex.ie/regulations/59#p3)). It must also:

- identify the public authority or third party responsible for establishing the supporting documents ([Regulation 59(4)](https://procurelex.ie/regulations/59#p4));
- contain a formal statement that the operator will be able, on request and without delay, to provide those documents ([Regulation 59(4)](https://procurelex.ie/regulations/59#p4));
- where the authority can obtain the documents directly from a database, give the information needed for that, such as the internet address of the database, identification data and, where applicable, the declaration of consent ([Regulation 59(5)](https://procurelex.ie/regulations/59#p5)).

Where the operator relies on the capacities of other entities under Regulation 63, the ESPD also contains the same information in respect of those entities ([Regulation 59(2)](https://procurelex.ie/regulations/59#p2)). The checks the authority then makes on them are described in the [guide to selection criteria](https://procurelex.ie/guides/selection-criteria).

For subcontractors, where necessary for the authority’s verification of grounds for exclusion under Regulation 71(8), the information on subcontractors is accompanied by their self-declarations under Regulation 59; subcontractors presented after award provide the certificates and supporting documents instead ([Regulation 71(5)](https://procurelex.ie/regulations/71#p5)).

## Form and reuse

The ESPD is provided exclusively in electronic form and drawn up on the basis of a standard form established by the Commission ([Regulation 59(7)](https://procurelex.ie/regulations/59#p7)). That paragraph did not apply until 18 April 2018 ([Regulation 59(13)](https://procurelex.ie/regulations/59#p13)).

An operator may reuse an ESPD already used in a previous procurement procedure, where it confirms that the information in it continues to be correct ([Regulation 59(6)](https://procurelex.ie/regulations/59#p6)).

## When the supporting documents are requested

The ESPD is preliminary evidence. The supporting documents come later, at one of two moments.

| When                             | What the authority does                                                                                                                                                      | Provision    |
| -------------------------------- | ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ------------ |
| At any time during the procedure | May ask a candidate or tenderer to submit all or any of the supporting documents, where necessary to ensure the proper conduct of the procedure                              | [Regulation 59(8)](https://procurelex.ie/regulations/59#p8) |
| Before awarding the contract     | Shall require the tenderer to which it has decided to award the contract to submit up-to-date supporting documents under Regulation 60 and, where appropriate, Regulation 62 | [Regulation 59(9)](https://procurelex.ie/regulations/59#p9) |

The duty before award does not apply to contracts based on a framework agreement concluded in accordance with Regulation 33(7) or (8)(a) ([Regulation 59(9)](https://procurelex.ie/regulations/59#p9)). The Directive (Article 59(4)) and the corresponding rule on reports ([Regulation 84(2)](https://procurelex.ie/regulations/84#p2)) also name Regulation 33(6), the framework agreement with a single operator, which Regulation 59(9) leaves out. See the [guide to framework agreements and dynamic purchasing](https://procurelex.ie/guides/framework-agreements-and-dynamic-purchasing).

The authority may invite an operator to supplement or clarify the certificates received under Regulations 60 and 62 ([Regulation 59(10)](https://procurelex.ie/regulations/59#p10)). More generally, where information or documentation is or appears incomplete or erroneous, or specific documents are missing, the authority may ask the operator to submit, supplement, clarify or complete it within an appropriate time limit, in full compliance with equal treatment and transparency ([Regulation 56(4)](https://procurelex.ie/regulations/56#p4)).

The invitation to tender or to participate in a dialogue must refer to any documents to be submitted in support of verifiable declarations under Regulations 59 and 60 and, where appropriate, 62 ([Schedule 6](https://procurelex.ie/regulations/schedule-6)).

## Which documents count as proof

The authority may require only the certificates, statements and other means of proof in Regulation 60 and Schedule 8 for exclusion and selection ([Regulation 60(1)](https://procurelex.ie/regulations/60#p1)), and no means of proof other than those in Regulation 60 and Regulation 62 ([Regulation 60(2)](https://procurelex.ie/regulations/60#p2)).

For the absence of exclusion grounds, it must accept as sufficient evidence ([Regulation 60(4)](https://procurelex.ie/regulations/60#p4)):

- for convictions under Regulation 57(1) and (2), an extract from the relevant register, including judicial records, or an equivalent document from a competent judicial or administrative authority;
- for taxes and social security under Regulation 57(3) to (5) and for insolvency under Regulation 57(8)(b), a certificate from the competent authority of the Member State or country of establishment.

Where the country does not issue such a document, or it does not cover all the cases, it may be replaced by a declaration on oath or, where there is no provision for that, a solemn declaration before a competent judicial or administrative authority, a notary or a competent professional or trade body ([Regulation 60(5)](https://procurelex.ie/regulations/60#p5)).

For selection, economic and financial standing is proved by the references in Part 1 of Schedule 8, or any other document the authority considers appropriate where the operator has a valid reason for not providing them, and technical ability by the means in Part 2 ([Regulation 60(6)](https://procurelex.ie/regulations/60#p6), [Regulation 60(7)](https://procurelex.ie/regulations/60#p7), [Regulation 60(8)](https://procurelex.ie/regulations/60#p8)). A certificate of registration on an official list or from a certification body may also be submitted ([Regulation 64(1)(a)](https://procurelex.ie/regulations/64#p1-a)).

## e-Certis

e-Certis is the online repository established by the Commission and referred to by that name in the Public Authorities Contracts Directive ([Regulation 61(2)](https://procurelex.ie/regulations/61#p2)). A contracting authority shall have recourse to e-Certis and require primarily the types of certificates or documentary evidence covered by it ([Regulation 61(1)](https://procurelex.ie/regulations/61#p1)). As made, that duty did not apply until 18 October 2018 ([Regulation 61(3)](https://procurelex.ie/regulations/61#p3)).

## When the operator need not supply documents

Two provisions displace the duty to submit supporting documents, notwithstanding paragraphs (8) and (9):

- **Free national databases.** An operator is not required to submit supporting documents or other documentary evidence where and in so far as the authority can obtain the certificates or information directly from a national database in any Member State that is available free of charge, such as a national procurement register, a virtual company dossier, an electronic document storage system or a prequalification system ([Regulation 59(11)](https://procurelex.ie/regulations/59#p11)).
- **Documents already held.** An operator is not required to submit supporting documents where the contracting authority having awarded the contract or concluded the framework agreement already possesses them ([Regulation 59(12)](https://procurelex.ie/regulations/59#p12)). This paragraph did not apply until 18 October 2018 ([Regulation 59(14)](https://procurelex.ie/regulations/59#p14)).

This is why the ESPD must give the database details of paragraph (5): they allow the authority to fetch the evidence itself.

## What happens if the documents do not come

An operator that is not able to submit the supporting documents required under Regulation 59, or that has seriously misrepresented or withheld the information for exclusion or selection, is in a situation in which the authority may exclude it ([Regulation 57(8)(h)](https://procurelex.ie/regulations/57#p8-h)). The same applies to negligently providing misleading information that may have a material influence on exclusion, selection or award ([Regulation 57(8)(i)](https://procurelex.ie/regulations/57#p8-i)). These grounds are discussed in the [guide to exclusion grounds](https://procurelex.ie/guides/exclusion-grounds).

## Dynamic purchasing systems

In a dynamic purchasing system, the authority may at any time during its validity require admitted participants to submit a renewed and updated self-declaration under Regulation 59(1) to (6) within 5 working days ([Regulation 34(24)](https://procurelex.ie/regulations/34#p24)), and Regulation 59(8) to (12) applies throughout the period of validity of the system ([Regulation 34(25)](https://procurelex.ie/regulations/34#p25)).

## Practical sequence

For a procurement officer, the Regulations suggest this order:

1. State the selection requirements and their means of proof in the contract notice or invitation to confirm interest ([Regulation 58(20)](https://procurelex.ie/regulations/58#p20)).
2. Accept the ESPD at submission as preliminary evidence ([Regulation 59(1)](https://procurelex.ie/regulations/59#p1)).
3. Request supporting documents during the procedure only where necessary for its proper conduct ([Regulation 59(8)](https://procurelex.ie/regulations/59#p8)).
4. Before award, require up-to-date supporting documents from the chosen tenderer, unless they can be obtained from a free database or are already held ([Regulation 59(9)](https://procurelex.ie/regulations/59#p9), [Regulation 59(11)](https://procurelex.ie/regulations/59#p11), [Regulation 59(12)](https://procurelex.ie/regulations/59#p12)).

Questions on electronic submission in general are answered in the [FAQ on electronic procurement](https://procurelex.ie/faq/electronic-procurement).