# Contract performance, modification and termination

- URL: https://procurelex.ie/guides/contract-performance-and-modification
- Updated 2026-11-20
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-20
- Legal basis: Regulation 70, Regulation 71, Regulation 72, Regulation 73, Regulation 18(4)

The conditions a contracting authority may attach to performance, what it must ask about subcontractors, when a contract or framework agreement may be modified without a new procedure, and the termination clauses every contract must contain.

The Regulations do not stop at the award. Chapter 4 of Part 2 governs the contract once it is running: the special conditions for its performance (Regulation 70), subcontracting (Regulation 71), modification during its term (Regulation 72) and the termination clauses every contract must contain (Regulation 73). Regulation 72 matters most in practice, because a change that falls outside it requires a new procurement procedure ([Regulation 72(8)](https://procurelex.ie/regulations/72#p8)).

## Conditions for performance

A contracting authority may lay down special conditions relating to the performance of a contract where they are linked to the subject matter of the contract within the meaning of Regulation 67(5) and are indicated in the call for competition or in the procurement documents ([Regulation 70(1)](https://procurelex.ie/regulations/70#p1)). They may include economic, innovation-related, environmental, social or employment-related considerations ([Regulation 70(2)](https://procurelex.ie/regulations/70#p2)).

Two consequences follow. A condition that was not announced cannot be added at the contract stage under this Regulation. And the link to the subject matter is the same test as for award criteria: a condition must relate to the works, supplies or services to be provided under the contract in any respect and at any stage of their life cycle ([Regulation 67(5)](https://procurelex.ie/regulations/67#p5)).

Separately from special conditions, every public contract must require the contractor to comply with the applicable obligations in the fields of environmental, social and labour law, established by European Union law, national law, collective agreements or the international conventions listed in [Schedule 7](https://procurelex.ie/regulations/schedule-7) ([Regulation 18(4)](https://procurelex.ie/regulations/18#p4)).

## Subcontracting

| Who                                                                                                   | What                                                                                                                                                         | Provision    |
| ----------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------ | ------------ |
| Contracting authority, in the procurement documents                                                   | May ask tenderers to indicate any share of the contract they intend to subcontract and any proposed subcontractors                                           | [Regulation 71(1)](https://procurelex.ie/regulations/71#p1) |
| Main contractor, in works contracts and services at a facility under the authority’s direct oversight | Must give the name, contact details and legal representatives of its subcontractors, so far as known, after award and no later than the start of performance | [Regulation 71(3)](https://procurelex.ie/regulations/71#p3) |
| Main contractor, during the contract                                                                  | Must notify changes to that information and the details of any new subcontractors                                                                            | [Regulation 71(4)](https://procurelex.ie/regulations/71#p4) |

Indicating subcontractors does not affect the main contractor’s liability ([Regulation 71(2)](https://procurelex.ie/regulations/71#p2)). The obligations in paragraphs (3) and (4) do not apply to suppliers ([Regulation 71(6)](https://procurelex.ie/regulations/71#p6)), but the contracting authority may extend them, for example to supply contracts, other services contracts, suppliers in works or services contracts, or subcontractors further down the chain ([Regulation 71(7)](https://procurelex.ie/regulations/71#p7)).

To avoid breaches of the environmental, social and labour obligations, the contracting authority may verify whether there are grounds for excluding subcontractors under Regulation 57 ([Regulation 71(8)](https://procurelex.ie/regulations/71#p8)). Where a subcontractor is caught by a compulsory exclusion ground, it shall require the economic operator to replace it; for a non-compulsory ground, it may require replacement ([Regulation 71(9)](https://procurelex.ie/regulations/71#p9)). For that verification, the information may need to be accompanied by the subcontractors’ self-declarations, and subcontractors presented after award provide certificates and supporting documents instead ([Regulation 71(5)](https://procurelex.ie/regulations/71#p5)). Where known, the share to be subcontracted and the names of the main contractor’s subcontractors go into the authority’s written report ([Regulation 84(1)(d)](https://procurelex.ie/regulations/84#p1-d)).

## Modification during the term

Regulation 72 applies to contracts and framework agreements, including contracts for social and other specific services awarded under Regulation 74 ([Regulation 72(1)](https://procurelex.ie/regulations/72#p1)). It also applies to contracts and framework agreements that are otherwise outside the Regulations under the transitional rules for procedures begun, or framework agreements concluded, before 18 April 2016 ([Regulation 86(4)](https://procurelex.ie/regulations/86#p4)).

### The grounds

A contract or framework agreement may be modified without a new procurement procedure in any of these cases ([Regulation 72(1)](https://procurelex.ie/regulations/72#p1)):

| Ground                                 | Conditions                                                                                                                                                                                                                                                                                                                       | Price cap                                                                                                 | Notice |
| -------------------------------------- | -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | --------------------------------------------------------------------------------------------------------- | ------ |
| Review clauses and options             | Provided for in the initial procurement documents in clear, precise and unequivocal clauses, which may include price revision clauses or options, stating the scope, nature and conditions of use, and not altering the overall nature of the contract ([Regulation 72(1)(a)](https://procurelex.ie/regulations/72#p1-a))                                                          | None: irrespective of value                                                                               | No     |
| Additional works, services or supplies | Necessary, not in the initial procurement, and a change of contractor cannot be made for economic or technical reasons and would cause significant inconvenience or substantial duplication of costs ([Regulation 72(1)(b)](https://procurelex.ie/regulations/72#p1-b))                                                                                                            | Each increase in price at most 50% of the original contract value ([Regulation 72(2)(a)](https://procurelex.ie/regulations/72#p2-a))                        | Yes    |
| Unforeseeable circumstances            | The need arises from circumstances a diligent contracting authority could not have foreseen and the overall nature of the contract is not altered ([Regulation 72(1)(c)](https://procurelex.ie/regulations/72#p1-c))                                                                                                                                                               | Each increase in price at most 50% of the original contract or framework agreement value ([Regulation 72(2)(b)](https://procurelex.ie/regulations/72#p2-b)) | Yes    |
| New contractor                         | Under an unequivocal review clause or option, or by universal or partial succession after corporate restructuring, including takeover, merger, acquisition or insolvency, to an operator meeting the original selection criteria, without other substantial modifications and not to circumvent the Regulations ([Regulation 72(1)(d)](https://procurelex.ie/regulations/72#p1-d)) | Not stated                                                                                                | No     |
| Non-substantial modification           | Not substantial within the meaning of paragraph (7) ([Regulation 72(1)(e)](https://procurelex.ie/regulations/72#p1-e))                                                                                                                                                                                                                                                             | None: irrespective of value                                                                               | No     |

For the 50% caps, where several successive modifications are made, the limit applies to the value of each, and consecutive modifications must not be aimed at circumventing the Regulations ([Regulation 72(2)](https://procurelex.ie/regulations/72#p2)).

### The de minimis ground

Paragraph (4) adds a further ground. Without any need to check the conditions in paragraph (7)(a) to (d), a contract may be modified without a new procedure where the value of the modification is below each of two values ([Regulation 72(4)](https://procurelex.ie/regulations/72#p4)):

- the thresholds of Regulation 5 (see the [thresholds](https://procurelex.ie/thresholds)) ([Regulation 72(4)(a)](https://procurelex.ie/regulations/72#p4-a));
- 10% of the initial contract value for service and supply contracts, or 15% for works contracts ([Regulation 72(4)(b)](https://procurelex.ie/regulations/72#p4-b)).

The modification may not alter the overall nature of the contract or framework agreement, and successive modifications are assessed on their net cumulative value ([Regulation 72(5)](https://procurelex.ie/regulations/72#p5)). Where the contract has an indexation clause, the updated value is the reference value for the percentage ([Regulation 72(6)](https://procurelex.ie/regulations/72#p6)).

The modification must be below both values. Paragraph (4) is read here as amended by S.I. No. 203 of 2017, which replaced the words “less than either of” with “below each of”, so a modification below only one of them cannot rely on this ground.

### When a modification is substantial

A modification is substantial where it renders the contract or framework agreement materially different in character from the one initially concluded ([Regulation 72(7)](https://procurelex.ie/regulations/72#p7)). In any event, it is substantial where one or more of the following is met:

1. it introduces conditions which, had they been part of the initial procedure, would have allowed the admission of other candidates, the acceptance of another tender, or attracted additional participants ([Regulation 72(7)(a)](https://procurelex.ie/regulations/72#p7-a));
2. it changes the economic balance in favour of the contractor in a way not provided for in the initial contract or framework agreement ([Regulation 72(7)(b)](https://procurelex.ie/regulations/72#p7-b));
3. it extends the scope considerably ([Regulation 72(7)(c)](https://procurelex.ie/regulations/72#p7-c));
4. a new contractor replaces the original one other than as permitted by paragraph (1)(d) ([Regulation 72(7)(d)](https://procurelex.ie/regulations/72#p7-d)).

Any other modification in circumstances outside paragraphs (1) to (5) requires a new procurement procedure ([Regulation 72(8)](https://procurelex.ie/regulations/72#p8)).

### Notices of modification

A contracting authority that has modified a contract on the ground of additional works, services or supplies or of unforeseeable circumstances must publish a notice in the Official Journal ([Regulation 72(3)](https://procurelex.ie/regulations/72#p3)). The notice contains the information in Part 7 of [Schedule 3](https://procurelex.ie/regulations/schedule-3), including a description of the procurement before and after the modification, any increase in price and the circumstances that made the modification necessary, and it is published in accordance with [Regulation 51](https://procurelex.ie/regulations/51). The Regulations require no such notice for the other grounds.

### Practical checklist

- Draft review clauses and options at the tender stage; like non-substantial modifications, they have no value limit and need no notice.
- Keep a running total of modifications for both the 50% caps and the de minimis ground.
- Record, for each modification, the ground relied on and the facts that meet its conditions.
- Check whether a notice of modification is due, and send it in accordance with Regulation 51.

## Termination

Every contract a contracting authority awards must contain provisions enabling it to terminate the contract during its term where ([Regulation 73](https://procurelex.ie/regulations/73)):

- the contract has been subject to a substantial modification which would have required a new procurement procedure under Regulation 72 ([Regulation 73(a)](https://procurelex.ie/regulations/73#pa));
- the contractor was, at the time of award, in one of the situations in Regulation 57(1) or (2) and should have been excluded ([Regulation 73(b)](https://procurelex.ie/regulations/73#pb));
- the contract should not have been awarded to the contractor in view of a serious infringement of the Treaties or the Regulations declared by the Court of Justice of the European Union in a procedure under Article 258 of the TFEU ([Regulation 73(c)](https://procurelex.ie/regulations/73#pc)).

The Regulations require the clauses; they do not set out the procedure for using them, which is a matter for the contract.

## Challenges

Review is governed by the Remedies Regulations (S.I. No. 130 of 2010), not by S.I. No. 284 of 2016; see the guide on [remedies](https://procurelex.ie/guides/remedies). As amended by S.I. No. 327 of 2017, they apply to contracts whose award is governed by S.I. No. 284 of 2016; they say nothing specific about modifications made during the term of a contract.