# Award, standstill and records

- URL: https://procurelex.ie/guides/award-and-standstill
- Updated 2026-11-20
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-20
- Legal basis: Regulation 55(1), Regulation 55(2), Regulation 55(3), Regulation 50(1), Regulation 50(2), Regulation 66(1), Regulation 84(1), Regulation 84(4), Regulation 84(5), Regulation 83(1)

What a contracting authority must do between the evaluation of tenders and the signed contract: informing candidates and tenderers, the standstill period, the contract award notice and the records it must keep.

Before concluding the contract, a contracting authority must tell candidates and tenderers what it has decided and let the standstill period run; after the award it must send a contract award notice for publication; throughout, it must keep a record that justifies each decision. The duties to inform, publish and keep records come from S.I. No. 284 of 2016. The standstill period, and the notice that starts it, come from the Remedies Regulations, S.I. No. 130 of 2010.

This guide describes S.I. No. 130 of 2010 as amended by S.I. No. 192 of 2015 and S.I. No. 327 of 2017. The 2017 amendments point it at S.I. No. 284 of 2016 in place of the 2006 Regulations, which [Regulation 85(1)](https://procurelex.ie/regulations/85#p1) revoked; neither instrument changed the standstill period.

## The sequence at a glance

| Step | What the contracting authority does                                                                            | Source                                  |
| ---- | -------------------------------------------------------------------------------------------------------------- | --------------------------------------- |
| 1    | Asks the tenderer it has decided to award the contract to for up-to-date supporting documents                  | [Regulation 59(9)](https://procurelex.ie/regulations/59#p9)                            |
| 2    | Informs each candidate and tenderer of the decision, as soon as possible                                       | [Regulation 55(1)](https://procurelex.ie/regulations/55#p1)                            |
| 3    | Sends each tenderer and candidate concerned a notice with a summary of reasons and the exact standstill period | Regulation 6 of S.I. No. 130 of 2010    |
| 4    | Waits at least 14 or 16 calendar days                                                                          | Regulation 5(4) of S.I. No. 130 of 2010 |
| 5    | Concludes the contract                                                                                         | Regulation 5(1) of S.I. No. 130 of 2010 |
| 6    | Sends the contract award notice within 30 days                                                                 | [Regulation 50(1)](https://procurelex.ie/regulations/50#p1)                            |
| 7    | Completes the written report and keeps the documentation                                                       | [Regulation 84(1)](https://procurelex.ie/regulations/84#p1), [Regulation 84(4)](https://procurelex.ie/regulations/84#p4)              |

Steps 2 and 3 are separate duties; a single letter serving as both must contain everything each requires.

## Before the decision

A contract is awarded on the award criteria once the contracting authority has verified that the tender complies with the contract notice and procurement documents and that the tenderer is not excluded and meets the selection criteria ([Regulation 56(1)](https://procurelex.ie/regulations/56#p1)). Before awarding, it must require the chosen tenderer to submit up-to-date supporting documents, except for certain contracts based on framework agreements ([Regulation 59(9)](https://procurelex.ie/regulations/59#p9)).

Where a competitive procedure with negotiation or a competitive dialogue proceeds in successive stages, the number of tenders or solutions is reduced by applying the award criteria stated in the procurement documents ([Regulation 66(1)](https://procurelex.ie/regulations/66#p1)), and the number left in the final stage must make for genuine competition in so far as there are enough tenders, solutions or qualified candidates ([Regulation 66(2)](https://procurelex.ie/regulations/66#p2)). Those selected and rejected at such a stage, with reasons, go into the written report ([Regulation 84(1)(b)](https://procurelex.ie/regulations/84#p1-b)).

## Informing candidates and tenderers (Regulation 55)

### The decision, as soon as possible

The contracting authority must inform each candidate and tenderer, as soon as possible, of a decision reached concerning the conclusion of a framework agreement, the award of a contract or admittance to a dynamic purchasing system ([Regulation 55(1)](https://procurelex.ie/regulations/55#p1)). Where applicable, it gives the grounds for any decision not to conclude a framework agreement, not to award a contract for which there has been a call for competition, to recommence the procedure, or not to implement a dynamic purchasing system ([Regulation 55(1)(c)](https://procurelex.ie/regulations/55#p1-c)).

### Reasons on request, within 15 days

On a request in writing, the contracting authority must answer as soon as possible and no later than 15 days after receiving it ([Regulation 55(2)](https://procurelex.ie/regulations/55#p2)):

| Who asks                                  | What it must be told                                                                                                                                                                                    |
| ----------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- |
| An unsuccessful candidate                 | The reasons for the rejection of its request to participate ([Regulation 55(2)(a)](https://procurelex.ie/regulations/55#p2-a))                                                                                                                            |
| An unsuccessful tenderer                  | The reasons for the rejection of its tender, including, in the cases of Regulation 42(10) and (11), the reasons for a decision of non-equivalence or that the requirements are not met ([Regulation 55(2)(b)](https://procurelex.ie/regulations/55#p2-b)) |
| A tenderer that made an admissible tender | The characteristics and relative advantages of the tender selected, and the name of the successful tenderer or the parties to the framework agreement ([Regulation 55(2)(c)](https://procurelex.ie/regulations/55#p2-c))                                  |
| A tenderer that made an admissible tender | The conduct and progress of negotiations and dialogue with tenderers ([Regulation 55(2)(d)](https://procurelex.ie/regulations/55#p2-d))                                                                                                                   |

### What may be withheld

Information may be withheld where its release would impede law enforcement or otherwise be contrary to the public interest, would prejudice the legitimate commercial interests of a particular economic operator, or might prejudice fair competition between economic operators ([Regulation 55(3)](https://procurelex.ie/regulations/55#p3)). The duty not to disclose information designated as confidential is without prejudice to Regulations 50 and 55 ([Regulation 21(2)(a)](https://procurelex.ie/regulations/21#p2-a)).

## The standstill period (S.I. No. 130 of 2010)

A contracting authority shall not conclude a contract to which a standstill period applies within that period (Regulation 5(1) of S.I. No. 130 of 2010). A contract is concluded when it has been entered into and is legally binding (Regulation 2(2)). No order of the Court may permit a contract to be concluded during the standstill period (Regulation 5(5), inserted in 2015).

### When it starts and how long it lasts

The period begins on the day after the day on which each tenderer and candidate concerned is sent the notice described below (Regulation 5(3)). It lasts at least 14 calendar days if that notice is sent by fax or electronic means, and at least 16 calendar days otherwise (Regulation 5(4)). A notice sent electronically on day 0 thus starts a period covering at least days 1 to 14. The [time limits table](https://procurelex.ie/deadlines) quotes these periods.

A tenderer is “concerned” unless it has been definitively excluded, which requires that the exclusion was notified under Regulation 6 and that either the Court has declared it lawful or it is not, or can no longer be, subject to a review procedure. A candidate is “concerned” if it was not told of the rejection of its application before the award decision was notified to the tenderers concerned (Regulation 2(3) and (4)).

### When there is no standstill period

Regulation 5(2) lists four cases: a contract for which S.I. No. 284 of 2016 does not require prior publication of a contract notice in the Official Journal; a contract where the only tenderer concerned is the one awarded the contract and there are no candidates concerned; a contract awarded on the basis of a framework agreement in accordance with [Regulation 33](https://procurelex.ie/regulations/33); and a specific contract based on a dynamic purchasing system in accordance with [Regulation 34](https://procurelex.ie/regulations/34) (Regulation 5(2)(c) and (d), as amended in 2017).

### The notice to unsuccessful tenderers and candidates

Regulation 6(2) requires the notice to:

1. inform the candidates and tenderers concerned of the decisions reached on the award, the framework agreement or admittance to the dynamic purchasing system, including the grounds for any decision not to award a contract for which there has been a call for competition, not to conclude a framework agreement, to recommence the procedure or not to implement a dynamic purchasing system;
2. state the exact standstill period applicable; and
3. include, for each unsuccessful candidate or tenderer, a summary of the reasons for rejecting its application or tender.

For an admissible tender, the summary comprises the characteristics and relative advantages of the tender selected, the name of the successful tenderer or the parties to the framework agreement and, in the cases of [Regulation 42(10)](https://procurelex.ie/regulations/42#p10) and [Regulation 42(11)](https://procurelex.ie/regulations/42#p11), the reasons for a decision of non-equivalence or that the requirements are not met (Regulation 6(3), as amended in 2017). Regulation 6(4) to (6) allows the summary to be given as scores, criterion by criterion, set against the successful tenderer or the lowest-scoring candidate or framework party that qualified. Regulation 6(7), as amended in 2017, allows information to be withheld on the same grounds as [Regulation 55(3)](https://procurelex.ie/regulations/55#p3), and nothing in Regulations 5 and 6 affects [Regulation 55](https://procurelex.ie/regulations/55) (Regulation 5A).

Whether the notice complies with Regulation 6(2) also affects the time limit for seeking a declaration of ineffectiveness: see the [guide on remedies](https://procurelex.ie/guides/remedies).

## The contract award notice (Regulation 50)

Not later than 30 days after the award of a contract or the conclusion of a framework agreement, the contracting authority must send for publication a contract award notice on the results of the procedure ([Regulation 50(1)](https://procurelex.ie/regulations/50#p1)). It contains the information in Part 4 of Schedule 3 and is sent in accordance with Regulation 51 ([Regulation 50(2)](https://procurelex.ie/regulations/50#p2)). That includes the type of procedure, with the justification for a negotiated procedure without prior publication, and the body responsible for review with precise information on the deadline for review procedures ([Schedule 3](https://procurelex.ie/regulations/schedule-3)).

- Where a prior information notice was the call for competition and no further contracts will be awarded in the period it covers, the award notice must say so ([Regulation 50(3)](https://procurelex.ie/regulations/50#p3)).
- For a framework agreement concluded under Regulation 33, no notice is needed for each contract based on it ([Regulation 50(4)](https://procurelex.ie/regulations/50#p4)).
- For a dynamic purchasing system, a notice is due within 30 days of each award, or notices may be grouped quarterly and sent within 30 days of the end of the quarter ([Regulation 50(5)](https://procurelex.ie/regulations/50#p5), [Regulation 50(6)](https://procurelex.ie/regulations/50#p6)).

Information may be withheld from publication on the grounds in [Regulation 50(7)](https://procurelex.ie/regulations/50#p7).

## Records and the written report (Regulation 84)

For every contract or framework agreement, and on establishing every dynamic purchasing system, the contracting authority prepares a written report ([Regulation 84(1)](https://procurelex.ie/regulations/84#p1)) recording at least:

- its name and address and the subject matter and value of the contract;
- the results of selection and any reduction of numbers, with names and reasons;
- the reasons for rejecting abnormally low tenders;
- the successful tenderer, why its tender was selected and, where known, the share to be subcontracted and the main subcontractors;
- the circumstances justifying a competitive procedure with negotiation, a competitive dialogue or a negotiated procedure without prior publication;
- where applicable, the reasons for not awarding, for not using electronic means, and conflicts of interest detected and measures taken.

No report is required for contracts based on framework agreements concluded under Regulation 33(6) and (7) or (8)(a) ([Regulation 84(2)](https://procurelex.ie/regulations/84#p2)), and the report may refer to the award notice to the extent the notice contains the information ([Regulation 84(3)](https://procurelex.ie/regulations/84#p3)).

Separately, the authority keeps documentation recording the progress of every procedure and justifying decisions at all stages, including communications with economic operators, internal deliberations, the preparation of the procurement documents, any dialogue or negotiation, and selection and award ([Regulation 84(4)](https://procurelex.ie/regulations/84#p4)), for at least 3 years from the date of award ([Regulation 84(5)](https://procurelex.ie/regulations/84#p5)). Oral communications that could substantially affect the content and assessment of tenders must be documented ([Regulation 22(7)(c)](https://procurelex.ie/regulations/22#p7-c)).

## Copies of concluded contracts (Regulation 83)

At least for the duration of the contract, the contracting authority keeps copies of concluded contracts worth €1,000,000 or more for supplies or services and €10,000,000 or more for works ([Regulation 83(1)](https://procurelex.ie/regulations/83#p1)). It must grant access to them ([Regulation 83(2)](https://procurelex.ie/regulations/83#p2)), subject to the applicable rules on access to documents and data protection ([Regulation 83(3)](https://procurelex.ie/regulations/83#p3)).

The Regulations apply to procurements with an estimated value equal to or greater than the [thresholds](https://procurelex.ie/thresholds) ([Regulation 5](https://procurelex.ie/regulations/5)); procurement below them is outside these Regulations.