# Contracts: performance, modification and termination

- URL: https://procurelex.ie/faq/contracts
- Updated 2026-11-20
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-20
- Legal basis: Regulation 70(1), Regulation 71, Regulation 72(1), Regulation 72(4), Regulation 72(7), Regulation 73

Answers on performance conditions, subcontracting, changing a contract during its term and the termination clauses every contract must contain.

These answers are on S.I. No. 284 of 2016, as amended by S.I. No. 203 of 2017.

## May a contracting authority impose conditions on how the contract is performed?

Yes. It may lay down special performance conditions linked to the subject matter of the contract, provided they are indicated in the call for competition or the procurement documents ([Regulation 70(1)](https://procurelex.ie/regulations/70#p1)). They may include economic, innovation-related, environmental, social or employment-related considerations ([Regulation 70(2)](https://procurelex.ie/regulations/70#p2)).
## Must a tenderer say whether it will subcontract?

Only if the procurement documents ask: the contracting authority may ask tenderers to indicate any share of the contract they intend to subcontract and any proposed subcontractors ([Regulation 71(1)](https://procurelex.ie/regulations/71#p1)). This does not affect the main contractor’s liability ([Regulation 71(2)](https://procurelex.ie/regulations/71#p2)).
## What must the main contractor tell the authority about its subcontractors?

In works contracts and services at a facility under the authority’s direct oversight, the name, contact details and legal representatives of its subcontractors, after award and no later than the start of performance ([Regulation 71(3)](https://procurelex.ie/regulations/71#p3)), and then any changes and any new subcontractors ([Regulation 71(4)](https://procurelex.ie/regulations/71#p4)). These obligations do not apply to suppliers ([Regulation 71(6)](https://procurelex.ie/regulations/71#p6)), although the authority may extend them ([Regulation 71(7)](https://procurelex.ie/regulations/71#p7)).
## Can the authority require a subcontractor to be replaced?

If it checks subcontractors for exclusion grounds under Regulation 57, it must require the replacement of one caught by a compulsory ground and may require the replacement of one caught by a non-compulsory ground ([Regulation 71(8)](https://procurelex.ie/regulations/71#p8), [Regulation 71(9)](https://procurelex.ie/regulations/71#p9)).
## When may a contract be changed without a new procurement procedure?

Only on the grounds of Regulation 72: review clauses or options in the initial procurement documents, necessary additional works, services or supplies, unforeseeable circumstances, a permitted change of contractor, or a modification that is not substantial ([Regulation 72(1)](https://procurelex.ie/regulations/72#p1)); or where the value of the change is under the de minimis values ([Regulation 72(4)](https://procurelex.ie/regulations/72#p4)). Any other modification needs a new procedure ([Regulation 72(8)](https://procurelex.ie/regulations/72#p8)). The [guide on modification](https://procurelex.ie/guides/contract-performance-and-modification) sets out each ground.
## Is there a limit on the price increase?

For additional works, services or supplies and for unforeseeable circumstances, each increase in price may not exceed 50% of the value of the original contract (or framework agreement, in the second case), and successive modifications must not be aimed at circumventing the Regulations ([Regulation 72(2)](https://procurelex.ie/regulations/72#p2)). Review clauses and non-substantial modifications apply irrespective of value ([Regulation 72(1)(a)](https://procurelex.ie/regulations/72#p1-a), [Regulation 72(1)(e)](https://procurelex.ie/regulations/72#p1-e)).
## What is the de minimis rule?

A contract may be modified where the value of the modification is below each of two values: the [thresholds](https://procurelex.ie/thresholds) of Regulation 5, and 10% of the initial contract value for service and supply contracts or 15% for works contracts ([Regulation 72(4)](https://procurelex.ie/regulations/72#p4)). The overall nature of the contract may not change and successive modifications are counted cumulatively ([Regulation 72(5)](https://procurelex.ie/regulations/72#p5)). As amended by S.I. No. 203 of 2017, which replaced “less than either of” with “below each of”, the change must be below both values.
## When is a modification substantial?

When it makes the contract materially different in character, and in any event where it would have let in other candidates, tenders or participants, shifts the economic balance to the contractor, extends the scope considerably, or replaces the contractor other than as permitted ([Regulation 72(7)](https://procurelex.ie/regulations/72#p7)).
## Must a modification be published?

A modification for additional works, services or supplies or for unforeseeable circumstances must be the subject of a notice in the Official Journal with the information in Part 7 of [Schedule 3](https://procurelex.ie/regulations/schedule-3) ([Regulation 72(3)](https://procurelex.ie/regulations/72#p3)). The Regulations do not require a notice for the other grounds.
## What termination clauses must every contract contain?

Clauses enabling the authority to terminate where the contract has been substantially modified in a way that required a new procedure, where the contractor should have been excluded under Regulation 57(1) or (2) at the time of award, or where the Court of Justice of the European Union has declared a serious infringement in a procedure under Article 258 of the TFEU ([Regulation 73](https://procurelex.ie/regulations/73)).